Service Manual

2 Maintenance (continued)

WARNING Follow the service and maintenance procedures given throughout this manual and in component literature shipped with the boiler. Failure to perform the service and maintenance could result in damage to the boiler

or system. Failure to follow the directions in this manual and component literature could result in severe personal injury, death, or substantial property damage.

WARNING The boiler should be inspected annually only by a qualified service technician. In addition, the maintenance and care of the boiler designated in Table 2A and explained on the following pages must be performed to assure maximum boiler efficiency and reliability. Failure to service and maintain the boiler and system could result in equipment failure.

WARNING Electrical shock hazard – Turn off power to the boiler before any service operation on the boiler except as noted otherwise in this instruction manual. Failure to turn off electrical power could result in electrical shock,

causing severe personal injury or death.

Address reported problems

Figure 2-1Condensate Trap

1.Inspect any problems reported by the owner and correct before proceeding.

Inspect boiler area

1.Verify that boiler area is free of any combustible materials, gasoline and other flammable vapors and liquids.

2.Verify that air intake area is free of any of the contaminants listed in Section 1 of the SYNC Installation and Operation Manual. If any of these are present in the boiler intake air vicinity, they must be removed. If they cannot be removed, reinstall the air and vent lines per this manual and the SYNC Installation and Operation Manual.

Inspect boiler interior

PVC TEE ASSEMBLY (FACTORY SUPPLIED)

TO FLOOR

DRAIN

2” PVC CAP WITH

BLOCKED DRAIN SWITCH

RETAINING

SCREW

CONDENSATE FROM HEAT EXCHANGER

1.Remove the front access cover and inspect the interior of the boiler.

2.Vacuum any sediment from inside the boiler and components. Remove any obstructions.

Clean condensate trap

1.

Inspect the condensate drain line, condensate PVC

 

fittings, and condensate trap.

2.

Remove the PVC cap retaining screw from the PVC cap

 

(FIG. 2-1).

3.

Remove the 2 inch PVC cap with the switch located at the

 

top of the trap (FIG. 2-1).

4.

Remove any sediment in the trap.

5.

Fill with fresh water until the water begins to pour out of

 

the drain.

6.

Replace the cap. Press the cap onto the trap until the cap

 

makes contact with the drain.

WARNING The condensate trap must be filled with water during all times of boiler operation

to avoid flue gas emission from the condensate drain line. Failure to fill the trap could result in severe personal injury or death.

Check all piping for leaks

WARNING Eliminate all system or boiler leaks. Continual fresh makeup water will

reduce boiler life. Minerals can build up in sections, reducing heat transfer, overheating heat exchanger, and causing heat exchanger failure. Leaking water may also cause severe property damage.

1. Inspect all water and gas piping and verify to be leak free.

2. Look for signs of leaking lines and correct any problems found.

3. Check gas line using the procedure found in Section 6 - Gas Connections of the SYNC Installation and Operation

7. Replace the retaining screw.

Manual.

37

Page 37
Image 37
Lochinvar 1 service manual Address reported problems, Inspect boiler area, Inspect boiler interior, Clean condensate trap

1 specifications

Lochinvar 1 is a remarkable achievement in the realm of modern technology and engineering. As a powerful and efficient water heater, it has been designed to cater to a wide range of residential and commercial needs. One of the standout features of Lochinvar 1 is its advanced heating technology, which incorporates a high-efficiency condensing design. This technology allows the unit to achieve impressive energy savings by maximizing heat transfer while minimizing energy consumption.

The Lochinvar 1 utilizes a stainless steel heat exchanger that enhances durability and corrosion resistance. This not only extends the lifespan of the unit but also ensures consistent performance over time. Coupled with a user-friendly control system, users can easily adjust settings and monitor performance, enhancing overall convenience and usability.

Another key characteristic of the Lochinvar 1 is its compact design, making it suitable for a variety of installation environments. Whether in a residential basement or a commercial utility room, the unit’s space-saving configuration allows for efficient use of available area without compromising on capability.

Safety features are integral to the Lochinvar 1, providing peace of mind for users. The unit is equipped with advanced monitoring systems that can detect irregularities and automatically shut down the system if necessary. This not only protects the equipment but also enhances the safety of the environment in which it operates.

In terms of performance, Lochinvar 1 boasts a high recovery rate, ensuring hot water is available on demand. This is particularly beneficial for settings with high water usage, allowing simultaneous operations without lag.

Moreover, the unit supports various venting options, offering flexibility during installation. Whether using traditional vertical venting or innovations like direct venting, Lochinvar 1 accommodates different building designs and local codes, making it highly versatile.

In conclusion, Lochinvar 1 epitomizes the melding of efficiency, reliability, and user-friendly technology. With its high-performance features, robust safety systems, and adaptable installation options, it stands out as a forefront player in the water heating industry, meeting the diverse needs of today's consumers and businesses alike.