Set Point Demand

To generate a setpoint demand, a voltage between 24 V (ac) and 230 V (ac) must be applied across the Setp / DHW and Com Dem terminals (8 and 7) (FIG. 26). The DHW MODE must be set to OFF.

9

10

 

Power

 

 

7

8

 

Com

Setp/

 

DHW

 

Dem

 

 

 

 

FIG. 26

External Input (0 - 10 V dc)

 

To generate an external input signal, a voltage between 0 and 10 V (dc) must be applied to the Com - and Out + ter- minals (1 and 4) (FIG. 27).

A 0 - 20 mA signal can be converted to a 0 - 10 V (dc) sig- nal by installing a 500 ohm resistor between the Com - and Out + terminals (1 and 4) (FIG. 27).

A 4 - 20 mA signal can be converted to a 2 - 10 V (dc) sig- nal by installing a 500 ohm resistor between the Com - and Out + terminals (1 and 4) (FIG. 27).

 

owerP

 

owerP

Do Not

Apply

Do Not

Apply

 

 

 

 

+

 

+

 

 

 

 

FIG. 27

￿OUTPUT CONNECTIONS

Primary Pump Contact (Prim P1)

The Prim P1 output terminal (11) is a powered output. When the relay in the control closes, 115 V (ac) is provided to the Prim P1 terminal (11) from the Power L terminal (10). To operate the primary pump, connect one side of the pri- mary pump circuit to terminal 11 and the second side of the pump circuit to the neutral (N) side of the 115 V (ac) power supply, see Figure 28.

9

10

11

 

Prim

Power

P1

 

L

 

 

 

 

FIG. 28

Combustion Air / Alarm Contact (C.A./Alarm)

The Combustion Air / Alarm Contact (C.A./Alarm) terminals (12 and 13) (FIG. 29) are an isolated output in the control. There is no power available on these terminals from the control. These terminals are to be used as a switch to either make or break power to the combustion air damper or alarm. Since this is an isolated contact, it may switch a volt- age between 24 V (ac) and 230 V (ac).

C.A./

Alarm

FIG. 29

Relay 1 to Relay 9

The Relay 1 to Relay 9 terminals (14 and 15 to 30 and 31) (FIG. 30) are isolated outputs in the control. There is no power available on these terminals from the control. These terminals are to be used as a switch to either make or break power to a boiler stage or a boiler pump. Since this is an isolated contact, it may switch a voltage between 24 V (ac) and 230 V (ac).

18

Page 18
Image 18
Lochinvar INS7162, MP2, INS7141 Set Point Demand, External Input 0 10 V dc, Primary Pump Contact Prim P1, Relay 1 to Relay