GENERAL INFORMATION

C. PRE-INSTALLATION REQUIREMENT

GENERAL

1.Munchkin Boilers are supplied complete- ly assembled as packaged boilers. The package should be inspected for damage upon receipt and any damage to the unit should be reported to the shipping com- pany and wholesaler. This boiler should be stored in a clean, dry area.

2.Carefully read these instructions and be sure to understand the function of all connections prior to beginning installa- tion. Contact your Munchkin Sales Representative or the Heat Transfer Products, Inc. Customer Service Department for help in answering ques- tions.

3.This boiler must be installed by a quali- fied contractor. The boiler warranty may be voided if the boiler is not installed cor- rectly.

CODES & REGULATIONS

Installation and repairs are to be performed in strict accordance with the requirements of state and local regulating agencies and codes dealing with boiler and gas appliance installation.

CODES & REGULATIONS WARNING

Liquefied Petroleum (LP) Gas or Propane is heavier than air and, in the event of a leak, may collect in low areas such as basements or floor drains. The gas may then ignite resulting in a fire or explosion.

ACCESSIBILITY CLEARANCES

1.The Munchkin Boiler is certified for clos- et installations with zero clearance to

combustible construction. In addition, it is design certified for use on combustible floors.

2.Refer to Figure 1.1 and Figure 1.2 for the recommended clearance to allow for rea- sonable access to the boiler. Local codes or special conditions may require greater clearances.

CAUTION

Do not install this boiler on carpeting.

COMBUSTION AND VENTILATION AIR

1.The Munchkin Boiler is designed only for operation with combustion air piped from outside (sealed combustion). PVC pipe must be supplied between the air inlet connection at the rear of the boiler through an outside wall.

2.No additional combustion or ventilation air is required for this appliance.

3.Refer to Section 4 of this manual, Venting, for specific instructions for pip- ing combustion air.

PLANNING THE LAYOUT

1.Prepare sketches and notes showing the layout of the boiler installation to mini- mize the possibility of interferences with new or existing equipment, piping, vent- ing and wiring.

2.The following sections of this manual should be reviewed for consideration of limitations with respect to:

a.Electrical Wiring: Part 2

b.Gas Connection: Part 3

c.Venting: Part 4

f.Piping: Part 5

8

Page 8
Image 8