3. Measure up so there will be at least 1/4" rise per foot of horizontal connector pipe, maintaining clearances to ceiling as noted in (Figure 12). This will give you center of hole for chimney penetration.

4. After locating

center of penetration, install tee-box and chimney as per chimney

manufacturer's

specifications.

5.Connect chimney connector to tee-box using #24 ga. minimum blue or black steel connector pipe. DO NOT use galvanized pipe. Connect each section so crimped end faces downward, and secure each section to each other using three (3) sheet metal screws or rivets. (See Figure 10. Page 15).

C.

Wall Exit Into Masonry Flue (Using Single Wall Pipe)

1.

Before connecting these units to a masonry chimney, determine that masonry flue pass-

 

through connector thimble meets

NFPA-211 Code and local building codes and is

 

a minimum of 18" from

ceiling. If

connector thimble does not meet these codes, pass

 

-through connector must

be modified.

 

 

NOTE: Floor protector

must be under horizontal pipe exit (See Figure 13. Page 19).

CEILING

CENTER LINE

 

 

OF ELBOW

1/4” RISE PER FT’

 

 

 

MARK PLUM LINE

 

SECURE WITH (3)

SEAL AROUND PIPE TO

 

SHEET METAL SCREWS

MASONRY

THIMBLE OR PASS-

 

THROUGH CONNECTOR

FLUE

 

WITH NON-COMBUSTIBLE

LINERS

 

MATERIAL

 

 

WALL

 

FLOOR PROTECTOR

Figure 12

CLEAN OUT

 

DOOR

See Figure 13. Page 17.

 

 

 

 

MASONRY CHIMNEY