YOUR ATS 46/53 BATTERY MACHINE HAS BEEN SHIPPED COMPLETE, BUT DO NOT ATTEMPT TO OPERATE WITHOUT FOLLOWING THESE INSTRUCTIONS.

PREPARING THE MACHINE FOR OPERATION

*Uncrate the machine and carefully remove from skid to prevent damage.

*The ATS 46/53 machines that are shipped without batteries have the (+) positive drive motor lead disconected.

*Open the battery compartment and connect the (+) positive motor lead to the top terminal post (the wire “P” is also attached to it). Tighten the terminal nut.

*Install the scrub brushes.

*Check the oil level in the hydraulic reservoir *Install batteries as follows (if not included):

1.Turn the key to the “OFF” position.

2.Raise the Solution Cover to the open position.

3.Use a battery lifting device with a 2500 lbs. (1150 Kg) capacity hoist to lift the battery.

4.Using the lifting device, lower the 36 volt battery into the battery compartment directly in front of the driver’s compartment. Orient the cables & plug them in as required.

5.Plug the polarized connector from the battery into the 36-volt plug provided.

PREPARING THE MACHINE FOR OPERATION WARNING

Hydrogen gas is formed during the charging operation and is explosive! Only charge batteries in a well-venti- lated area with the lid open. Avoid any open flame or electrical sparks. Pulling out the charger plug with the timer on will cause an arc and must be avoided.