Page 10 of 46 Preinstallation preparation
•System Engineering (553-3001-151)
•Power Engineering (553-3001-152)
After the site has been planned, the following items must be completed prior to ISDN BRI installation.
•Wire the building between ISDN BRI terminal locations and the distribution frame. Refer to the “Engineering guidelines” section of ISDN Basic Rate Interface: Product Description
•Install any IPE or Network Modules needed to house ISDN BRI cards as determined in “Engineering guidelines” of ISDN Basic Rate Interface: Product Description
Unpack and inspect
ISDN BRI cards and external communication cables are shipped in separate packages. To unpack them, follow the general precautions recommended by computer and telephone equipment manufacturers.
•Remove items that generate static charge from the installation site.
•If the installation site is carpeted, spray it with an antistatic spray.
•Ground yourself before handling any equipment.
•Carefully remove the equipment from its packaging. Do not puncture or tear the containers. Use scissors or a utility knife.
•Inspect the equipment for obvious faults or damage. Report any damaged component to your sales representative and the carrier who delivered the equipment.
•When unpacking the circuit cards, hold them only by their