Prerequisites

36Ethernet Routing Switch 8310 and 8306 chassis installation

Prerequisites

Provide adequate space around the unit for access to cable connectors.

Ensure that the surface can safely support the weight of the chassis, its components, and its attached cables. See “Chassis installation time requirements” (page 35).

Procedure steps

Step Action

1Set the switch on the flat surface and check for proper ventilation.

Allow at least 2 inches 5.1 cm) on each side for proper ventilation and 5 inches (12.7 cm) at the front for power cord clearance.

2Attach rubber feet to each marked location on the bottom of the chassis.

The rubber feet are optional but recommended to keep the unit from slipping.

3Attach all devices to the ports.

--End--

Procedure job aid: Chassis weight including components

The following table shows the weight of each chassis including the components.

Chassis

Maximum weight (chassis and components)

 

 

8310

225 pounds (lb) (102 kilograms [kg])

 

 

8306

140 lb (63 kg)

 

 

Mounting the Ethernet Routing Switch 8310 and 8306 chassis in an equipment rack

Install the Ethernet Routing Switch 8310 and 8306 chassis in a standard 19-inch equipment rack to provide a convenient location for the safe operation of the switch.

ATTENTION

If you are mounting the chassis in a 23-inch equipment rack, see the rack manufacturer’s 23-inch-to-19-inch rack adapter installation instructions.

Nortel Ethernet Routing Switch 8300

Installation — Chassis

NN46200-309 01.01 Standard

16 June 2008

Copyright © 2008 Nortel Networks

Page 36
Image 36
Nortel Networks 8310 Prerequisites, Procedure job aid Chassis weight including components, Procedure steps, Step Action