Welcome to the OutBack Power Systems FX Series
Inverter/Charger System
The FX Series Inverter/Charger offers a complete power conversion
OutBack Power Systems does everything possible to assure the components you purchase will function properly and safely when installed as instructed according to local and national electrical codes. Please read all of the following instructions and the instructions that come with any OutBack components in- cluded in your power system. Further instructions on individual FX
The OutBack Power Systems FX Series Inverter/Charger is ETL listed to UL1741 (Inverters, Converters, Con- trollers, and Interconnection System Equipment for Use with Distributed Energy Resources). All Mobile FX Series Inverter/Chargers are ETL listed to UL 458
Grounding Instructions – Each FX should be connected to a grounded, permanent wiring system. For most installations, the negative battery conductor should be bonded to the grounding system at one (and only one) point in the DC system. All installations must comply with all national and local codes and ordinances. System grounding as required by the National Electric Code, ANSI /NFPA
The equipment ground is marked with this symbol:
The
IMPORTANT SAFETY INSTRUCTIONS
General Precautions
1.Use caution whenever working around electricity, electrical components, and batteries. There is always a potential for shocks, burns, injury, and even death if an installer or user comes in contact with electricity.
2.Read all instructions and cautionary markings on the FX, the batteries and all appropriate sections of this manual as well as other component manuals before using the system.
3.Be sure each system FX is securely installed according to the FX and VFX Series Inverter/Charger Installation Manual.
4.Follow all local and national electrical codes when installing OutBack equipment and components.
Note:
•Neither the GTFX nor the GVFX is designed to be used with a generator. They are strictly for
•An OutBack MATE is required to program the FXs beyond their default values.
•If an OutBack Charge Controller is in use, be sure to read its manual for optimum operation with a
•When powered up, the GTFX/GVFX will automatically sense if a utility grid is present and then connect to it after a 30- second delay. There is a
•Ul 1741 requires approved surge protection for a
4