PB Heat DE manual Electrical, D.Sequence Of Operation, 2 Wiring and Connection Diagram

Models: DE

1 43
Download 43 pages 63.1 Kb
Page 21
Image 21
Figure 6.2: Wiring and Connection Diagram

ELECTRICAL

Figure 6.2: Wiring and Connection Diagram

D.SEQUENCE OF OPERATION

1.Thermostat calls for heat, energizes Control Relay (CR).

2.Control Relay (CR) energizes circulator.

3.Limit senses boiler water temperature. Prevents boiler operation until water temperature falls approximately 15°F (8°C) below the cut-out temperature.

4.Limit energizes Fan and Isolation Relay (IR).

5.Negative pressure induced by fan switches Pressure Switch, continuing power through closed contacts (IR-1) and flame roll-out switch.

6.Gas valve energizes. a. Igniter on.

b.Pilot gas on, igniting pilot.

7.Pilot flame detected.

a.Igniter off.

b.Main gas on, igniting main burners.

Note: If pilot flame is not detected within 30 seconds, the igniter is turned off for 30 seconds, and then turned back on. If the pilot is not detected within 30 seconds, the igniter and pilot gas are turned off for 5 minutes. The sequence then resumes at Step 6a.

8.Call for heat ends.

a.Pilot and main gas off, extinguishing pilot and main burners.

b.Fan and circulator off.

19

Page 21
Image 21
PB Heat DE manual Electrical, D.Sequence Of Operation, 2 Wiring and Connection Diagram