INSTALLATION
GAS CONNECTION
The gas connection is a 1/2 inch BSP Male thread. The gas line can be rigid copper pipe. Pipe size to ensure correct operating pressure. For minimum and maximum supply pressure see the System Data table below.
Note: During any pressure testing of the gas supply piping system that exceeds test pressures of 3.45 kPa, this ap- pliance and its individual
INSTALLATION IS TO BE CARRIED OUT ONLY BY AN AUTHORISED PERSON
SYSTEM DATA
|
| NG | LPG | |
| Injector size | # 36 | # 52 |
|
| Input Rating | 33 mj | 33 mj | |
|
|
|
|
|
| Manifold Pressure | 0.8 kPa | 2.38 kPa | |
|
|
|
|
|
|
|
|
|
|
4)Light the pilot and turn the valve to "ON" position.
5)The pressure check should be carried out with the unit burning and the setting should be within the limits specifi ed on the safety label.
6)When fi nished reading manometer, turn off the gas valve, discon- nect the hose and tighten the screw (clockwise) with a 1/8" fl at screwdriver. Screw should be snug, but do not over tighten.
VALVE DESCRIPTION
1)Gas on/off knob
2)Manual high/low adjustment
3)Pilot Adjustment
4)Thermocouple Connection
5)Main Operator
6)Outlet Pressure Tap
7)Inlet Pressure Tap
8)Pilot Outlet
9)Main Gas Outlet
GAS PIPE PRESSURE TESTING
The appliance must be isolated from the gas supply piping system by closing its individual manual
The manifold pressure is controlled by a regulator built into the gas control, and should be checked at the pressure test point.
Note: To properly check gas pressure, both inlet and manifold pressures should be checked using the valve pressure ports on the valve.
1)Make sure the valve is in the "OFF" position.
2)Loosen the "IN" and/or "OUT" pressure tap(s), turning counter- clockwise with a 1/8" wide fl at screwdriver.
3)Attach manometer to "IN" and/or "OUT" pressure tap(s) using a 5/16" ID hose.
10)Flange Securing Screw Holes
11)Alternative TC Connection Point
12)Thermoelectric Unit
13)Additional Valve Mounting Hole
Regency® | 9 |