Charging the refrigerant and preventing refrigerant leakage
1.Measure the quantity of the refrigerant according to the length of the liquid side pipe. Then, Add fixed quantity of the refrigerant using a scale. (When the pipe length exceeds the standard pipe length of 5 m, charge the additional amount of refrigerant according to the exceeding length. Do not charge the refrigerant by assuming the quantity through pressure gage or by any other method.
| Refrigerant amount | ||
Model name | Standard (less | Additional (over | |
5m) | 5m) | ||
| |||
| g | g/m | |
AF55JS✴ Series | 3100 | 30 | |
AF55JV✴ Series | 2600 | 30 | |
AC036KXQPCC | 2400 | 30 | |
AC048KXQPCC | 2600 | 30 |
| Manifold gage | Outdoor unit |
|
| High |
| |
Low | pressure |
|
|
Gas side |
|
| |
pressure |
|
| |
service |
|
| |
|
| I06nstallation | |
| valve |
| |
|
| Liquid side | |
|
|
| |
| Vacuum | service valve |
|
|
|
| |
| pump |
|
|
| Scale |
|
|
However, if the pipe length is shorter than the standard length, you do not need to charge the additional refrigerant.)
2.Open the manifold gauge valve connected to the liquid side service valve and add the liquid refrigerant.
3.If you cannot add the refrigerant while the outdoor unit is stopped, open the gas side and liquid side service valve and add remaining refrigerant by pressing the cooling trial operation button.
4.After charging the refrigerant, completely open the spindle of the service valve (in
5.Tighten the cap of the service valve on gas side pipe and liquid side pipe as well as the cap nut for the charging port.
Outer | Tightening torque | ||
diameter | Body cap (N•m) | Charging port cap | |
(mm) | (N•m) | ||
|
6.3520 ~ 25
9.5220 ~ 25
12.7 | 25 ~ 30 | 10 ~ 12 |
15.8830 ~ 35
19.0535 ~ 40
Tightening torque for body cap (Refer to the
table for torque of each radius)
Spindle
Charging core
Tightening torque for charging port cap (Refer to the table for torque of each radius)
❋❋1 N•m = 10 kgf•cm