Marathon 810 (ST9816AG) Product Manual, August 1995

15

 

 

 

2.0Drive mounting and configuration

2.1Handling and static-discharge precautions

After unpacking, and before installation, the drive may be exposed to potential handling and ESD hazards. It is mandatory that you observe standard static-discharge precautions. A grounded wrist-strap is pre- ferred.

Handle the drive only by the sides of the head/disc assembly. Avoid contact with the printed circuit board, all electronic components and the interface connector. Do not apply pressure to the top cover. Always rest the drive on a padded antistatic surface until you mount it in the host system.

2.2 Jumper settings

2.2.1Master/slave configuration

You must establish a master/slave relationship between two drives attached to a single AT bus. You can configure a drive to become a master or slave by setting the master/slave jumpers, as described below and shown in Figure 2 on page 16.

Alternatively, you can configure the drive as a master or slave using the cable select option. This requires a specialized daisy-chain cable that grounds pin 28 (CSEL) on one of its two drive connectors. If you attach the drive to the grounded CSEL connector, it becomes a master. If you attach the drive to the ungrounded CSEL connector, it becomes a slave. To use this option, the host system and both drives must support cable select and both drives must be configured for cable select. To configure an ST9816AG for cable select, install both master/slave jumpers.

For the host to recognize the slave drive using the DASP– signal, the slave drive must assert the DASP– signal at power up, and the master drive must monitor DASP– at power up.

Page 23
Image 23
Seagate 810 manual Drive mounting and configuration, Handling and static-discharge precautions