Site Preparation

5

Before You Start

Make sure the opening dimensions, door clearance, electrical service and plumbing are correct for the model you are about to install. Refer to specifications on the following pages.

IMPORTANT NOTE: To operate properly, the door must open a minimum of 90°. Use a minimum 3" (76) filler in corner installations to assure a 90° door opening. Allow enough clearance in front of the unit for full door swing.

subzero.com/specs

TOOLS AND MATERIALS REQUIRED

Appliance dolly able to support 130 lbs (59 kg)

Level — 2' (.6 m) and 4' (1.2 m) recommended

Phillips and slotted screwdriver sets

Wrench set and allen wrench set

Crescent wrenches

Various sized pliers

5/16" hex bolt nut driver

Drill and assorted drill bits

Model UC-24CI—4' (1.2 m) of 1/4" copper, braided stainless steel or PEX tubing and saddle valve for water line (do not use self-piercing valves).

Model UC-24CI—Tubing cutter.

Masonite, plywood, 1/8" pressed fiberboard, cardboard or other suitable material to protect finished flooring