2 9 4 9 5 A irp o rt R o a d , E u g e n e , O R 9 7 4 0 2 T e l:(5 4 1 ) 4 6 1 - 6 0 2 0 F a x :(5 4 1 ) 4 6 1 - 6 0 2 3 T o ll F re e : 1 - 8 0 0 - 6 2 4 - 4 8 0 9
Factory Authorized PowerMax Start-Up
Verification Worksheet
Job Name:______________________________________________________________
Job Location:____________________________________________________________
Dealer Name:___________ Serial # ___________________
! Verify incoming water temperature to booster heater is 110Ε to 140Ε. ! Verify size of vent piping. ____” dia.
! Is there any horizontal vent piping? YES / NO (Circle one) How much? _____ ft.
! Is vent pipe correct pipe for application?
! If an auxiliary power vent is being used, is it installed with an indirect connection, per drawing?
Exhaust
!If used, is power vent installed and operating correctly? YES / NO (Circle One)
!Must come on with burner and continue for 4 minutes after burner shutdown.
!Verify electrical connection to unit is correct and to NEC code.
!Verify size, volume, pressure and type of gas supply & that they are in accordance with manufacturers specification: 3.25"w.c. NG or 8"w.c. LP; Check at test port on gas
!
!
!
!
!
!
!
valve.
Verify gas supply pipe size. _____” dia.
Verify pipe size, flow pressure and volume of water supply to unit according to manufacturers specifications. Water supply pipe size. _____” dia.
Does dishwasher have
Verify that pipe length from booster accumulator outlet or circulating loop to rinse valve does not exceed 5 feet. (NSF maximum) and is correct diameter (both supply and return)
_____” dia.
Verify that unit has been flushed properly; both water & gas piping. Check all gas connections for leaks.
Check all water connections for leaks.
24