• Installation •
5 Complete block assembly
Install burner mounting plate on front section
1.Install four ½" x 4¾" studs to secure burner mounting plate to section:
a.Thread and lock together two nuts on rounded end of stud. Thread flat end of stud into one of four holes located around opening.
b.Remove nuts.
c.Repeat steps a and b for remaining studs.
2.Install burner mounting plate:
a.Apply 1/8" continuous bead of sealing rope adhesive in groove around opening in section.
b.Position ½" sealing rope in groove. Overlap ends at least one inch.
c.Install burner mounting plate. Use ½" washers and nuts.
Install observation port assemblies on front and back sections:
1.Install front observation port assembly:
a.Apply 1/8" continuous bead of sealing rope adhesive in groove on observation port.
b.Position 3/8" sealing rope in groove.
c.Secure assembly to section. Use 5/16 " - 18 x ¾" slotted head screws.
2.Repeat above steps for back observation port assembly.
Install cleanout plates
Cleanout plates must be installed
1.See Figure 7. Position two ¼" x 1¾" carriage bolts in cleanout opening. Secure with washers and nuts.
2.Place blanket insulation piece against cleanout plate.
3.Mount cleanout plate over opening. Secure with nuts and washers.
4.Repeat steps 1 through 3 for remaining cleanout plates.
The boiler contains ceramic fiber and | Figure 7 Cleanout plate assembly |
fiberglass materials. Use care when |
|
handling these materials per |
|
instructions on page 38 of this |
|
manual. Failure to comply could |
|
result in severe personal injury. |
|
Part No. | 9 |