INSTALLATION INSTRUCTIONS

COMMISSIONING

1. COMMISSIONING

After connecting the gas pipe to the stove:

1.1PURGE THE SUPPLY PIPE to dispel any debris that might block the controls.

1.2Connect the gas supply to the 8mm compression elbow at the right-hand rear corner of the stove (see Diagram 1).

1

AR0934

1.3Connect a suitable pressure gauge to the test point on the inlet fitting.

1.4Turn on the gas supply.

1.5Light the stove and check all gas joints for leaks.

1.6Turn the stove to maximum to check the supply pressure corresponds with the data badge information.

1.7Turn the gas off.

1.8Replace the test point screw.

1.9Turn the gas on.

1.10Check the test point for leaks.

To finish commissioning:

1.11Check the stove complies with all local regulations.

1.12Check all seals are in good condition.

1.13Complete the Appliance Commissioning Checklist on page 3.

1.14Show the user how to operate the stove.

1.15Hand the completed instructions to the User for safe keeping. The information is required when making any guarantee claims.