York D2EG 060 Cooling System, Preliminary Operation Cooling, Cooling Sequence Of Operation

Models: D2EG 048 D2EG 060 D3EG 036

1 20
Download 20 pages 61.22 Kb
Page 13
Image 13
OPERATION

035-14832-003-A-0204

OPERATION

COOLING SYSTEM

The cooling section is a complete factory package utilizing an air-cooled condenser. The system is factory-charged with Refrigerant-22.

The compressor is hermetically sealed and internally sprung. The compressors have inherent (internal) protection. If there is an abnormal temperature rise in the compressor, the protector will open to shut down the compressor.

PRELIMINARY OPERATION COOLING

After the installation has been completed, energize the crankcase heater (3 ton only) for at least 4 hours before operating the unit. After this initial warm-up, the compressor should be given three false starts (energized just long enough to make a few revolutions) with a 5 minute delay between each start before being put into full time service.

NOTE: Prior to each cooling season, the crankcase heater (3 ton only) must be energized at least 10 hours before the system is put into operation.

COOLING SEQUENCE OF OPERATION

Single-Stage Cooling: When the thermostat calls for “cooling”, “R” is closed to “G” and “Y1" (wiring schematic) which completes the low voltage control circuit, immediately energizing the compressor, condenser fan motor and blower motor simultaneously.

Two-Stage Cooling: A two-stage cooling thermostat may be used if the unit has an economizer. First-stage cooling is provided by the economizer - if the outdoor air enthalpy is acceptable, and second-stage cooling is provided by the compressor. Jumper wire J1 must be removed. Refer to the unit wiring diagram.

After the thermostat is satisfied and opens, the blower will continue to run for a short time. All other components will stop.

CONTINUOUS BLOWER - Continuous blower operation is possible by closing the R to G circuit on the thermostat.

SAFETY CONTROLS (Cooling)

The refrigerant system is equipped wth the following safety controls:

1.A Suction Line Freezestat to protect against low evapora- tor temperature due to low air flow or a low return air tem- perature.

2.A High Pressure Cutout Switch to protect against excessive discharge pressures due to a blocked condenser coil or a condenser motor failure.

3.A Low Pressure Switch to protect against loss of refrigerant charge.

If neither one of the above safety controls opens, the refrigerant system will be locked out. The lock out of the system can be reset by opening the 24V circuit either at the room thermostat or at the unit disconnect.

HEATING SEQUENCE OF OPERATION

The following sequence describes the operation of the gas heat section.

CONTINUOUS BLOWER: With the room thermostat switch set to “ON”, the supply air blower will operate continuously. The normally closed blower interlock relay contact “K3-1" provides 24 volt power to the blower relay ”BR". The “BR” power contacts close and the blower motor operates.

INTERMITTENT BLOWER: With the room thermostat system switch set to the “AUTO” or “HEAT” position and the fan switch set to “AUTO”, the supply air blower will operate after the room thermostat calls for heat and the air in the gas heat compartment has achieved a pre-set temeprature.

When “TH1" on the thermostat closes, the draft motor relay ”DMR" or “DMC” is energized. The “DMR” or “DMC” power contacts close which energizes the line voltage draft motor. As the speed of the draft motor reaches approximately 2500 RPM, the centrifugal switch contact “CS” located on the end of the draft motor shaft closes to power the ignition control “IC”.

After 15 seconds the “IC” will start the ignitor sparking and will open the redundant valve locted inside the main gas valve “GV” to allow a flow of gas to only the carryover tube. See Figure 10. Only after the pilot flame has been ignited and the presence of pilot flame detected at the “IC” by a signal sent back through the flame sensor is sparking terminated and the main gas valve opened.

REDUNDANT

 

MAIN VALVE

VALVE

 

 

GAS MAIN

 

GAS

 

TO MAIN

VALVE

TO PILOT BURNER

BURNER

 

 

FIG. 10 - GAS VALVE PIPING

Gas flows into each of the main burners and is ignited from the carryover tube flame.

The “IC” will try for 85 seconds to ignite the pilot carryover tube. If the “IC” fails to detect a pilot flame during the 85 seconds, it will close the redundant valve. After a 5 minute purge period, the “IC” will again try to light the pilot carryover tube. This will continue continuously until the “IC” detects a pilot flame.

If, after detecting a pilot flame and opening the main gas valve, the “IC” looses pilot flame indication, it will close both the main and redundant gas valves. The “IC” will start the above sequence over until a pilot flame is detected and it will open the main gas valve again.

The “IC” will only allow 16 pilot flameouts and a single rollout switch opening per thermostat cycle. After 16 pilot flameouts or a single rollout switch opening, the “IC” closes both the main and redundant gas valves. The “IC” requires resetting the thermostat or removal of it's power lead coming from the draft motor to reset the “IC” and return it to the above sequence of operation.

At the same time power was supplied to the “DMR” or “DMC”, a parallel circuit activates the time delay relay “BT” or “ETD”. The “BT” or “ETD” closes in approximetly 35 seconds and starts the circulating air blower by energizing the blower interlock relay “K3", thus closing the ”K3-2" contact and energizing the blower relay “BR”.

When the heating cycle is complete, “TH-1" opens de- energizing the “IC”, thus closing the redundant and main gas valves. The blower motor and the draft motor continue to run for a short period after the furnace is shut down until the “BT” or “ETD” opens (in approximately 25 seconds) de-energizing the “K3", ”BR" and “DMR” or “DMC” relays.

Unitary Products Group

13

Page 13
Image 13
York D2EG 060 Cooling System, Preliminary Operation Cooling, Cooling Sequence Of Operation, SAFETY CONTROLS Cooling