4.7SCHEDULED MAINTENANCE

Following is a recommended maintenance schedule for QuietSource small standby and residential generator sets. The established intervals in the schedule are the maximum recommended when the unit is used in an average service application. They will need to be decreased (performed more frequently) if the unit is used in a severe appli- cation. Use calendar time from the previous maintenance interval to determine the next required maintenance interval.

Service Maintenance Interval Information:

The various service maintenance intervals are designated by interval numbers as follows:

1An early inspection of the generator set to ensure it is ready to operate when required and to identify any poten- tial problem areas.

Performed monthly, this procedure requires approximately .5 man-hours per unit to complete.

This inspection may be performed by the end user providing the following safety steps are taken to prevent the engine from starting automatically without warning:

To prevent injury, perform the following steps in the order indicated before starting any maintenance:

Disable the generator set from starting and/or connecting to the load by setting the control panel AUTO-OFF-MANUAL switch to the “OFF” position.

Remove the control panel fuse.

Turn off the battery charger.

Remove the negative battery cable.

The battery charger must be turned off BEFORE removing the battery cable to prevent an over current condi- tion from burning out sensitive control panel components and circuits.

Following all maintenance, reverse these steps to insure the unit is returned to standby setup for normal operation when required.

2A break-in service inspection of the generator set to ensure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed ONLY ONCE following the first three months after purchase of the unit and requires approxi- mately 2.5 man-hours per unit to complete.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an authorized Generac Service Dealer.

3An operational inspection of the generator set to ensure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed semi-annually, this procedure requires approximately 1.5 man-hours per unit to complete.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an authorized Generac Service Dealer.

4A mid-level inspection of the generator set to ensure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed annually, this procedure requires approximately 4.0 man-hours per unit to complete.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an authorized Generac Service Dealer.

NOTE:

If the generator experiences heavy use, the maintenance intervals should be reduced so that procedures are performed more frequently.

Generac® Power Systems, Inc. 19

Image 21
Contents Liquid-cooled, Prepackaged Standby Generators ‹ Operation and Maintenance Authorized Service Dealer Location‹ HOW to Obtain Service IntroductionTable of Contents General Hazards Electrical Hazards Generator Transfer SwitchAutomatic System Operation Generator AC Connection Systems‹ 1.7.2 High Coolant Temperature Switch ‹ 1.7.1 LOW OIL Pressure Switch‹ 1.7.3 LOW Coolant Level Switch Generator Fuel SystemLifting the Generator UnpackingReconfiguring the Fuel System Specifications‹ 1.10.1 Generator Specifications ‹ 1.10.2 Engine SpecificationsBefore Installation Torque SpecificationsEngine OIL Recommendations Coolant RecommendationsGenerator Mounting Support Generator LocationBasic Standby Electric System ‹ 2.1.1 Nfpa StandardsEmergency Circuit Isolation Method Transfer Switch Signal ConnectionsTotal Circuit Isolation Method Generator AC Neutral ConnectionsBattery Installation ‹ 2.9.2 GTS-TYPE Engineered Transfer Switch‹ 2.10.1 Vented Batteries Preparation Before START-UP Using AN Engineered GTS Transfer Switch‹ 3.2.2 Fault Indicator LED ‹ 3.2.1 AUTO/OFF/MANUAL Switch‹ 3.2.5 SET Exercise Time Switch Control Console ComponentsRetransfer and Shutdown Manual Transfer START-UP Engine Governor AdjustmentsAutomatic Operation Weekly Exercise CycleOverload Protection for Engine DC Electrical System Cooling SystemChecking Fluid Levels ‹ 4.5.10 Changing Engine OIL ‹ 4.5.11 Changing the Engine AIR Cleaner‹ 4.5.12 Spark Plugs ‹ 4.5.13 Coolant Change‹ 4.6.1 Cleaning the Generator Miscellaneous Maintenance‹ 4.6.2 Battery ‹ 4.6.4 Battery ReplacementService Maintenance Interval Information Scheduled MaintenanceLevel Maintenance Level Problem Cause Correction Troubleshooting PointsInstallation Diagram Electrical Data Electrical Data Electrical Data Electrical Data Carrier Rear Bearing Hold Down Battery Assy WireBoot Battery Cable Battery Post Covwer BlackSee Latch Detail ASSEMBLY,BASE-DOOR Ground Wire Assy GRD Wire 99HSBDuct Intake MID AL Duct Discharge RH ALGenerac Power Systems, Inc Control BOX HSB Assy 2A 12V UL BatteryCover Front Panel HSB Cover TOP Panel HSB ShockGenerac Power Systems, Inc Assembly Resistor Cover Flywheel AccessFlexplate 3.9L HSB SunkPump Radiator Copper Brass Tank Coolant RecoveryVENTURI,3.9L Cryslr HSB 22FAN Radiator Support L/H SideTo Engine Hold Down AIR Cleaner Base AIR Cleaner PlatePlate AIR Cleaner TOP Flange Fuel InletLeads Rotor 390 40KW 1P Direct HSB Rotor 390 30KW 1P Direct HSBSTR-390--40AD HSB 433MM LONG3.9L Chrysler Rear Bearing Carrier 390/DRCTWYE, Pipe 3.9L Chrysler OUTNUT TOP Lock FL M12-1.75 Pipe L/H Exhaust ManifoldQuietsource 40kW Liquid-cooled Generators Quietsource 40kW Liquid-cooled Generators Quietsource 40kW Liquid-cooled Generators This Warranty Shall not Apply to the Following