3M 2600 manual Cable Preparation, Ribbon Preparation, Construction Color

Page 6

3.0 Cable Preparation

3.01Remove sheath from the end of the cable per case instructions. A minimum of 8 ft. (2.4 m) is typically required.

3.02Clean gel from the ribbons with cleaning pads in the 3M brand 4415 Service Wire Cleaning Kit. Wipe ribbon dry with towels provided in the kit.

Note: Carefully follow safety, health, and disposal information on cleaning pad label or Material Safety Data Sheet.

3.03 Install breakout kit if required per company practice.

3.04 Secure cable to the splice case or distribution panel housing.

4.0 Ribbon Preparation

4.01Ribbon is constructed in four different ways: bonded, ribbonized, encapsulated, and Adhesive Sandwich Ribbon. It is important to identify the type of construction so that the proper tube guide and ribbon holder can be selected.

Bonded construction has a thin layer of material that holds the fibers together. Examples are AT&T XAR Accuribbon 12 fiber and Alcatel 12 fiber Uniribbon.

Ribbonized construction is performed in the field using individual fibers and adhesive tape.

Encapsulated construction has a thick layer of material all around the fibers. Examples are NTT 2, 4, and 8 fiber ribbon.

Adhesive Sandwich Ribbon construction is used only in AT&T 12 fiber ASR ribbon. It has a polyester tape construction that is wider than the fibers.

4.02 Select the proper size tube guide from the chart.

 

 

3M Part #

Construction

Color

 

 

2634

12 fiber bonded or ribbonized

Light Yellow

 

 

2635

12 fiber AT&T ASR

White

 

 

 

 

 

 

 

 

 

2637

10 fiber bonded or ribbonized

Light Gray

 

 

 

 

 

 

 

 

 

2639

8 fiber bonded or ribbonized

Light Blue

 

 

2640

8 fiber encapsulated

Dark Blue

 

 

 

 

 

 

 

 

2641

6 fiber bonded or ribbonized

Light Green

 

 

 

 

 

 

 

 

2645

4 fiber bonded or ribbonized

Light Red (Pink)

 

 

2646

4 fiber encapsulated

Dark Red

 

 

4.03 Install the tube guide into the stripper handle.

Note: If necessary, remove the tube lock with the removal tool.

Pull the tube guide out with your fingers.

6

Image 6
Contents Instructions Page Contents 265 673 Color Code GeneralPreparation Kit Product Number Fiber CountCable Preparation Ribbon PreparationConstruction Color Page Ribbon Holder Preparation Application ColorCleaver Operation Page Visual Inspection of the Cleave Fiber Insertion Applying the Pre-load Splice Actuation Not CenteredMulti-Fiber Stripper Cleaning and Maintenance Page Helpful Hints Splice Preparation Kits Splice Organizer Trays and AccessoriesOrdering Information System Components/Spare PartsPage 3M Telecom Systems Group Important Notice