Preparation

4.0PREPARATION

These installation instructions provide all the information needed for positioning the Nfinity Mainte- nance Bypass Cabinet (including environmental requirements) and for connecting the input and out- put power cables.

4.1Inspection

Upon receiving the Nfinity Maintenance Bypass Cabinet, examine the packaging for any signs of mis- handling or damage. If any damage is noted, contact your local dealer or Liebert representative and notify your carrier.

4.2Environment

The Maintenance Bypass Cabinet environment must be free of conductive contaminants and exces- sive moisture (water condensation), flammable vapors, chemical fumes, or corrosive gases and liquids.

4.3Required Setup Equipment

The tools below are required in order to properly setup your maintenance bypass cabinet:

pallet jack

1/2" (13 mm) wrench

torque wrench

flat-head screwdriver

#2 Phillips screwdriver

3/16" (5 mm) Allen wrench

4.4Site Preparation

When deciding where to locate your Maintenance Bypass Cabinet, consider the weight and size of the unit. Make sure that the structural integrity of the floor can withstand the weight. Refer to the table below for dimensional considerations:

Table 2

Maintenance Bypass Cabinet physical data

 

 

 

 

 

 

 

 

Dimensions

 

 

Model

 

With Transformer

 

Without Transformer

 

W x D x H

 

9.5 x

26.5 x 30.4

 

In (mm)

 

(241.3 x 673.1 x 772.16)

 

Weight

 

287 lbs (130 kg)

 

85 lbs (38 kg)

 

Check to make sure that your Maintenance Bypass Cabinet will be located in a well-ventilated area with at least 12 inches (304mm) in front of and behind it. Transformer based models are forced air cooled with the aid of two internal cooling fans.

Figure 5 Clearances

12" (304mm)

12" (304mm)

9

Image 13
Contents GXT 10KVA Page Table of Contents Specifications MaintenanceImportant Safety Instructions Glossary of Symbols General Description System DescriptionFront view Rear view without transformer Rear view with transformer Bypass Mode UPS ModeModes of Operation User Selectable Output Distribution Bypass SwitchMajor Components Inspection Required Setup EquipmentEnvironment Site PreparationUnloading Unloading the Maintenance Bypass CabinetStationary Mounting Preparing Internal Wiring Wiring PreparationDual Source Configuration Cable InstallationMaintenance Bypass Cabinet with transformer Removing the Cover Plates Power Cable InstallationRepo Connection Conduit Input and Output WiringElectrical connections-transformer model MBC Electrical connections-non-transformer model MBC Connecting Nfinity to Maintenance Bypass with transformer Connecting Nfinity to Maintenance Bypass without transformer GXT10000T-208X GXT10000T-240X Shutting Down the UPS Start-Up and InitializationOperation Maintenance Scheduled MaintenanceProper Care General & Environmental Rating SpecificationsSpecifications Specifications Page Company Behind the Products Technical Support/ServiceLocations