Emerson GXT 10KVA Wiring Preparation, Preparing Internal Wiring, Dual Source Configuration

Page 16

Cable Installation

6.0CABLE INSTALLATION

6.1Wiring Preparation

! WARNING

Please read this section thoroughly before attempting to install wiring to this unit.

Be sure that the unit is not connected to any AC mains power source or UPS before installing any wir- ing to this unit. This Maintenance Bypass Cabinet should be installed by a qualified / certified electri- cian.

6.2Preparing Internal Wiring

The Maintenance Bypass Cabinet is factory-configured for single-source installations. If your installa- tion requires dual-source capabilities, the Maintenance Bypass Cabinet’s wiring must be modified.

6.3Dual Source Configuration

Modifying the wiring consists of removing the jumpers between TB1 and TB2 as described below:

1.Remove cover plates.

2.Identify TB1 and TB2.

3.Using a 3/16" Allen wrench, loosen terminal mounting jumpers between TB1 and TB2.

4.Remove jumpers and retighten terminals to 50 in-lb.

5.Connect primary source to TB2 and secondary source to TB1.

Figure 6 Jumper removal—transformer models and non-transformer models

TRANSFORMER MODELS

GEC

TB1

 

 

 

 

 

 

TB2

 

 

 

TB3

 

 

 

 

 

Cables to be removed

 

 

 

 

 

 

 

 

 

 

 

 

NON-TRANSFORMER MODELS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TB1

Cables to be removed

TB2

 

 

 

 

 

 

12

 

Image 16
Contents GXT 10KVA Page Table of Contents Maintenance SpecificationsImportant Safety Instructions Glossary of Symbols System Description General DescriptionFront view Rear view without transformer Rear view with transformer Bypass Mode UPS ModeModes of Operation User Selectable Output Distribution Bypass SwitchMajor Components Required Setup Equipment InspectionEnvironment Site PreparationUnloading the Maintenance Bypass Cabinet UnloadingStationary Mounting Wiring Preparation Preparing Internal WiringDual Source Configuration Cable InstallationMaintenance Bypass Cabinet with transformer Removing the Cover Plates Power Cable InstallationRepo Connection Input and Output Wiring ConduitElectrical connections-transformer model MBC Electrical connections-non-transformer model MBC Connecting Nfinity to Maintenance Bypass with transformer Connecting Nfinity to Maintenance Bypass without transformer GXT10000T-208X GXT10000T-240X Shutting Down the UPS Start-Up and InitializationOperation Maintenance Scheduled MaintenanceProper Care Specifications General & Environmental RatingSpecifications Specifications Page Company Behind the Products Technical Support/ServiceLocations