Emerson GXT 10KVA user manual Start-Up and Initialization, Shutting Down the UPS, Operation

Page 26

Operation

7.0OPERATION

7.1Start-Up and Initialization

To start up the Nfinity UPS while it is connected to the Nfinity Maintenance Bypass:

1.Set the Maintenance Bypass switch (SW1) to the UPS position on the Maintenance Bypass Cabinet.

2.Close the UPS source switch (SW2).

3.Close the output circuit breaker (CB1).

4.Close the input circuit breaker (CB1).

5.On the UPS, close the control enable switch (SW2).

6.After the UPS has initialized, turn the UPS output on by pushing the Standby button.

7.2Shutting Down the UPS

To power down the UPS system:

1.Turn the UPS output Off by pushing the Standby button.

2.Open the Control Enable switch (SW2) on the UPS.

3.Open the input circuit breaker (CB1) on the UPS.

4.Open the UPS Source switch (SW2) on the Maintenance Bypass Cabinet.

5.Open the output circuit breaker (CB1) on the Maintenance Bypass Cabinet.

7.3Transferring the System from UPS to Maintenance Bypass Operation

1.Verify that the amber Bypass lamp is illuminated

2.Turn the Bypass Switch (SW1) to the bypass position on the Maintenance Bypass Cabinet. The connected equipment is now powered from the bypass source and is not protected.

7.4Transferring the System from Maintenance Bypass to UPS Operation

1.Close the UPS Source Switch (SW2) on the Maintenance Bypass Cabinet.

2.Close the input circuit breaker (CB1) on the UPS.

3.Close the Control Enable Switch (SW2) on the UPS.

4.Turn the UPS output On by pushing the Standby button on the UPS.

5.Verify that the green UPS lamp is illuminated.

6.Turn the Bypass Switch to the bypass position on the Maintenance Bypass Cabinet.

22

Image 26
Contents GXT 10KVA Page Table of Contents Maintenance SpecificationsImportant Safety Instructions Glossary of Symbols System Description General DescriptionFront view Rear view without transformer Rear view with transformer Modes of Operation UPS ModeBypass Mode Major Components Bypass SwitchUser Selectable Output Distribution Environment Required Setup EquipmentInspection Site PreparationUnloading the Maintenance Bypass Cabinet UnloadingStationary Mounting Dual Source Configuration Wiring PreparationPreparing Internal Wiring Cable InstallationMaintenance Bypass Cabinet with transformer Repo Connection Power Cable InstallationRemoving the Cover Plates Input and Output Wiring ConduitElectrical connections-transformer model MBC Electrical connections-non-transformer model MBC Connecting Nfinity to Maintenance Bypass with transformer Connecting Nfinity to Maintenance Bypass without transformer GXT10000T-208X GXT10000T-240X Operation Start-Up and InitializationShutting Down the UPS Proper Care Scheduled MaintenanceMaintenance Specifications General & Environmental RatingSpecifications Specifications Page Locations Technical Support/ServiceCompany Behind the Products