Emerson 610 installation manual Equipment Location

Page 14

Equipment Location

4.0EQUIPMENT LOCATION

1.Handle cabinet(s) in accordance with the safety precautions in this manual, especially in these sections:

Battery Cabinet Precautions—inside front cover

Important Safety Instructions—page 1

2.0 - Unloading and Handling—page 6

5.0 - Battery Installation—page 9

Use a suitable material handling device to move the cabinet to its final location. Exercise extreme care because of the uneven weight distribution. Carefully lower the cabinet to the floor.

2.Referring to Shipping Split Detail (Figures 38 through 43), and any other drawings that are associated with switchgear, set cabinets in final position, preparatory to reconnection of shipping split power and control wiring/bus.

3.Verify that the UPS system is installed in a clean, cool and dry location.

4.Installation and serviceability will be easier if adequate access is provided on all sides of the equipment, but only front access is required.

a.Verify that there is adequate clearance to open cabinet doors—4 ft. (1.2m) is recommended. NEC requires sufficient clearance in front of the equipment to fully open all doors without restriction. See drawings and local codes. SCCT requires front and rear or one-side access for installation and maintenance.

b.Verify that there is adequate area in front of circuit breakers to perform maintenance. Check installation drawings for location of breakers. Check with local codes.

c.Verify that there is adequate clearance above all cabinets to allow exhaust air to flow without restriction. The minimum clearance is 2 ft. (0.6m), unobstructed by conduit or any other items. Liebert recommends against using upflow air conditioning systems or any system that blows air down onto the top of the modules.

5.Align the UPS cabinet, battery cabinets (if used) and optional transformer and maintenance bypass cabinets, as shown in the Line-Up Detail drawing (Figure 46) and your submittal package.

6.Referring to Shipping Split Details (Figures 38 through 43 and your submittal package for SCC/ Switchgear drawings), connect cabinets together mechanically.

7.Referring to Shipping Split Details (Figures 38 through 43 and your submittal package for SCC/ Switchgear drawings), connect intercabinet ground straps, power wiring and bus interconnects. Internal control connections should be left disconnected for later installation by Liebert LGS Customer Engineers.

8

Image 14
Contents Liebert Series 610 UPS Battery Cabinet Precautions Contacting Liebert for SupportTable of Contents Figures Iii Tables Important Safety Instructions Page Installation Considerations Multi-Module 500 to 750kVA UPS Types of System Control Cabinets System Control CabinetsUnloading and Handling Inspections External InspectionsInternal Inspections and Shipping Material Removal Equipment Location Battery Safety Precautions Battery InstallationBattery Safety Precautions in French Per CSA Requirements AvertissementBattery Cabinets Open-Rack Batteries Configuring Your Neutral and Ground Connections Preferred Grounding Configuration, Wye-Connected Service Preferred grounding configuration, wye-connected serviceAlternate Grounding Configuration, Wye-Connected Service Alternate grounding configuration, wye-connected servicePreferred Grounding Configuration With Isolated Bypass Preferred grounding configuration with isolated bypassAlternate Grounding Configuration, Non-Isolated Alternate grounding configuration, non-isolatedConfiguring Your Neutral and Ground Connections Preferred grounding configuration, impedance-grounded wye Preferred Grounding Configuration, Battery Systems Preferred grounding configuration, battery systemsWiring Considerations Power Wiring Scct Control Wiring Abbreviations for circuit breakersBattery Wiring Wiring Connections Specific ConnectionsWiring Connections Wiring Inspection Power wiring terminals, factory suppliedField-supplied lugs 16, National Electrical Code Reprint Installation Drawings 97-797600-176 Rev 88-797658-84 Rev 88-797658-94 Rev 88-797657-26 Rev 88-797657-95 Rev Outline drawing, 500kVA Multi-Module UPS, 12-pulse rectifier 88-797657-92 Rev 88-797668-84 Rev 88-797668-90 Rev 88-797665-29 Rev 88-797665-90 Rev 88-797656-66 Rev 88-797656-86 Rev 88-797668-66 Rev 88-797668-86 Rev 88-797664-68 Rev 88-797664-88 Rev 88-797677-65 Rev Base mounting patterns, 500kVA module, 6-pulse rectifier Base mounting patterns, 500kVA module, 12-pulse rectifier 88-797613-28 Rev Base mounting patterns, 625-750kVA module, 6-pulse rectifier 88-797613-29 Rev 88-797613-19 Rev 88-797613-27 Rev Shipping split detail, 500kVA, 12-pulse rectifier 88-797612-08 Rev Shipping split detail, 625-750kVA, 6-pulse rectifier 88-797612-09 Rev Shipping split detail, 625-750kVA, 12-pulse rectifier 88-797612-07 Rev Battery power pack system Battery power pack, Size a 88-797607-63 Rev Outline drawing, System Control Cabinet SCCT, 200-1200A 88-797613-71 Rev Outline drawing, System Control Cabinet SCCT, 1600-2000A 88-797613-78 Rev Outline drawing, System Control Cabinet SCCT, 2500-3000A 88-797613-73 Rev Outline drawing, System Control Cabinet SCCT, 4000A Base mounting patterns, System Control Cabinet SCCT, 4000A 96-797619-58A Rev 96-797619-66A Rev Control connection location diagram, Scct 96-797619-51A Rev 96-797619-60 Rev 96-797619-19A Rev 96-797619-20 Rev 96-797619-21 Rev 96-797619-130 Rev 96-797619-28 Rev 96-797619-128 Rev 96-797619-62 Rev 96-797619-90 Rev 96-797619-91 Rev 96-797619-52A Rev 96-797619-53A Rev 96-797619-54A Rev 96-797619-55A Rev 96-797619-56A Rev 96-797619-57A Rev 88-797616-09 Rev 88-797616-13 Rev 88-797616-07 Rev Outline drawing, remote status panel, surface mount Installation Drawings Data, Series 610, 500-750kVA, Multi-Module Systems Site planning data-600V input Site planning data-480V input System Control Cabinets Page Page Page Environmental Systems 800-543-2778 Outside the United States