SECTION 3 TESTING & SERVICE

PREVENTIVE MAINTENANCE

Reasonable care in preventive maintenance will insure high reliability and long life for the automatic transfer switch.

Operate the switch at least once a month. Perform this four step Electrical Operation Test. This is a test with load transfer.

DISCONNECTING THE CONTROLLER

The harness disconnect plugs are furnished for repair purposes only and should not have to be unplugged. If the controller must be isolated, follow these steps carefully.

Disconnecting the Plugs

Do not unplug the controller until step

1a. or 1b. below is completed.

1.Observe the position of the transfer switch.

a.If the transfer switch is in the Normal position, place standby engine starting control in the off position. Then open the emergency source circuit breaker.

b.If the transfer switch is in the Emergency position, open the normal source circuit breaker. Place the engine starting control in the test or run position.

2.Separate the quick disconnect plugs by squeezing the latches. Do not pull on the harness wires.

Transfer Switch Test

1.Press and hold the door-mounted Transfer Test button until the engine starts and runs. This should happen within 15 seconds.

2.The transfer switch will operate to the Emergency position. If the Transfer To Emergency Delay is used, the transfer will occur after a time delay (up to 5 minutes). For immediate transfer press Bypass Time Delay button.

3.The Transfer Switch will operate back to the Normal position after the Retransfer To Normal Delay (up to 30 minutes). For immediate retransfer press Bypass Time Delay button.

4.Unloaded Running (Engine Cooldown) Delay allows engine to run unloaded for 5 minutes.

Clean and inspect the switch once a year. De-energize all sources, then brush and vacuum away any excessive dust accumulation. Remove the transfer switch barriers and check contact condition. Replace contacts when pitted or worn excessively. Reinstall the barriers carefully.

Maintain transfer switch lubrication. The transfer switch has been properly lubricated, and under normal operating conditions no further lubricating is required. Renew factory lubrication if the switch is subjected to severe dust or abnormal operating conditions. Relubricate the operator if TS coil is replaced. Order lubrication kit 75-100.

Replacement parts. Replacement parts are available in kit form. When ordering parts provide the Serial No. and Catalog No. from the transfer switch nameplate. Contact your local ASCO Power Technologies sales office, representative, or ASI. In the United States call 1–800–800–ASCO (2726), or in Canada call 1–888–234–ASCO (2726).

3---1

3.Label, remove, and tape the signal wires connected to the engine start terminals on the transfer switch: TB1 and TB3, or TB1 and TB2.

Reconnecting the Plugs

Do not reconnect the controller until step 1a. or 1b. and 2 below are completed.

1.Observe the position of the transfer switch.

a.If the transfer switch is in the Normal position, be sure that the standby engine starting control is still in the off position. The emergency source circuit breaker still should be open.

b.If the transfer switch is in the Emergency position, normal source circuit breaker still should be open.

2.Reconnect the signal wires connected to the appropriate engine start terminals on the transfer switch. See Section 1, Engine Starting Contacts.

3.The harness plugs and sockets are keyed. Carefully align the plugs with the sockets and press straight in until both latches click.

4.Restore the opposite source as follows:

a.If the transfer switch is in the Normal position, place the standby engine starting control in the automatic position. Then close the emergency source circuit breaker.

b.If the transfer switch is in the Emergency position, close the normal source circuit breaker. The load will be automatically retransferred to the normal source after the Retransfer to Normal Delay. For immediate retransfer, press Bypass Time Delay button. Place the engine starting control in the automatic position.

Image 11
Contents Operator’s Manual 600 800 1000 1200 Nameplate Catalog Number IdentificationController Membrane controls Rating LabelPage Section InstallationConnections to Controller InstallationEngine Starting Contacts Auxiliary CircuitsManual Operation Test Installation Functional TestATS Position Handle Indicators Voltage Checks Close the enclosure door first Electrical OperationTransfer To Emergency Sequence of OperationDisconnecting the Controller Testing & ServicePreventive Maintenance Manual Load Transfer Testing & ServiceTROUBLE-SHOOTING Proceed with care Automatic transfer switch is energizedTime Delay Settings AdjustmentsTime Delay Adjustment Sensor AdjustmentsClose the enclosure door AdjustmentsHow to Change a Setting BUILT-IN Engine Exerciser Control Features Engine ExercisersDIP Switch Settings How to Set Built-In TimerProgrammable Engine Exerciser Module Control FeaturesNavigating the Menu Daylight Savings Time Adjust DisplayFast / Slow Adjust Display Fill in your settings for future referenceLoad Disconnect Feature Remote Control FeaturesInphase Monitor For Motor Load Transfer Controls Control Features Optional Strip Heater AccessoryStrip Heater Accessory Available Kits from AscoIndex