5.4Checking Operation after Installation and Preparing the HDDs for Use

5.4.1Checking initial operation

The procedure for verifying operation after power-on is explained below.

(1)Initial diagnosis at the time of power-on:

a)When the HDDs are turned on, the Active LED blinks and the HDDs perform the initial self- diagnosis (controller hardware diagnosis).

b)When the SAS protocol controller diagnosis is completed normally, the HDDs start the LINK RESET sequence defined by the SAS protocol to establish synchronization with the connected SAS devices (e.g., the host system).

c)When the initial diagnosis is completed normally, the HDDs can respond to commands from the host.

(2)Verifying interface connection:

When verification of initial operation after power-on is completed normally, the host system checks whether the HDD connection to the interface is normal. The procedure for this check depends on the host system configuration. The following is a general check procedure:

a)Confirm that the transfer rate and HDD SAS addresses can be recognized during the LINK RESET sequence.

b)Issue the INQUIRY, WRITE BUFFER, and READ BUFFER commands to verify that data is received and transmitted normally in the interface.

(3)Verifying disk drive operation :

When the LINK RESET sequence has completed, the host system can issue a spindle motor start instruction and check whether the disk drive is ready to operate.

a)The host system instructs the spindle motor to start by sending the NOTIFY (ENABLE SPINUP) primitive to the disk drive.

b)The HDDs do not start the motor until the NOTIFY (ENABLE SPINUP) primitive is issued.

c)The disk drive enters the READY state within about 60 seconds after the NOTIFY (ENABLE SPINUP) primitive is issued.

d)The HDD Active LED blinks (flashes on and off every 0.5 seconds) while the motor is running.

e)The Active LED remains lit when the HDDs enter the READY state. The host system can use the TEST UNIT READY command to confirm that the HDDs are in the READY state.

(4)Responses to operation errors :

a)Confirm again that connectors are securely attached to cables.

b)Check whether the supply voltage is supplied normally. (Measure the voltage at the power connectors of the HDDs.)

5-4

C141-E237

Image 58
Contents C141-E237-01EN For Safe Operation Revision Record Related Standards Preface Overview of ManualPreface Conventions for Alert MessagesImportant Alert Items Important Alert MessagesImportant Alert Items Data lossManual Organization Product Maintenance ManualSpecifications InterfaceThis page is intentionally left blank Contents Installation ContentsGL-1 Figures Tables This page is intentionally left blank Standard Features Hardware Structure System Configuration Standard FeaturesGeneral Description Standard Features General Description Hardware Structure System Configuration Hardware Specifications Model name and order number Hardware SpecificationsModel names and order numbers Function specifications SpecificationsMAX3147RC MAX3073RC MAX3036RC Hardware Specifications Environmental specifications Environmental/Power requirementsReliability Error rateMtbf = Specifications Data Space Logical Data Block Addressing Defect Management Cylinder configurationData Space Data Format Data Space Alternate spare area Spare area in cellTrack format Track skew/head skew Sector formatData Space Format capacity Logical Data Block Addressing Defect Management Defect list Alternate block allocationAlternate block allocation by Format Unit command Defect ManagementAlternate block allocation by Reassign Blocks command Write Write Extend Write Write Extended Format Unit Installation Requirements Mounting Requirements DimensionsInstallation Requirements Mounting orientationsMounting Requirements Mounting frame structure exampleLimitation of side-mounting HDC Surface temperature check point and maximum temperatureMPU Service clearance area Power Supply Requirements Current waveform +12V DCInterface connector CN1 power lines included Interface connector Connection RequirementsInterface connector SAS plug signal allocationCN1 Ready LED output signal 11 Recommended external circuit for Ready LED outputThis page is intentionally left blank Installation Installation Setting Port Address SettingMounting Drives Mounting procedures Installation Formatting Installation Setting parameters Arre AwreArre Awre PER Xffff DiscXxxx Dismounting Drives Diagnostics Self-diagnostics Self-diagnostic functionsDiagnostics and Maintenance Diagnostics Test programs Maintenance Information PrecautionsMaintenance requirements Maintenance levels Revision numbersIndicating revision numbers Tools and test equipment Test flowchart TestsOperation Check Initial seek operation check Diagnostic testOperation test Troubleshooting Procedures Troubleshooting with disk drive replacement in the fieldSystem-level field troubleshooting Troubleshooting at the repair site Disk drive troubleshootingTroubleshooting with parts replacement in the factory Finding possibly faulty partsError Analysis Information Collection Sense Data Analysis Error Analysis Information Collection Sense dataLSB Error AnalysisILI SksvSense Data Analysis Definition of sense dataSense data 1-1x-xx, 3-1x-xx and E-1D-00 Disk read error Sense data 3-0C-03, 4-32-01, 4-40-xx, 4-C4-xx,Glossary Glossary Target TargAcronyms and Abbreviations Acronyms and Abbreviations VPDBcrc ECCMtbf Mttr Mode SELECT/MODE SelectIndex PADC141-E237 IN-3 This page is intentionally left blank Comment Form This page is intentionally left blank