Chapter 2 Preparing for Installation
Site Preparation Checklist
Table
Task No. Planning Activity | Verified By Time | Date |
1Space evaluation:
•Space and layout
•Floor covering
•Impact and vibration
•Lighting
•Maintenance access
2Environmental evaluation:
•Ambient temperature
•Humidity
•Altitude
•Atmospheric contamination
•Airflow
3Power evaluation:
•Input power type
•Power receptacles (depends on power supply)1
•Receptacle proximity to the equipment
•Dedicated (separate) circuits for redundant power supplies
•Proper gauge wire and lugs
4Grounding evaluation:
•Circuit breaker size
•CO ground
5Cable and interface equipment evaluation:
•Cable type
•Connector type
•Cable distance limitations
•Interface equipment (transceivers)
6EMI evaluation:
•Distance limitations for signaling
•Site wiring
•RFI levels
1.Verify that each power supply installed in the chassis has a dedicated AC source or DC source circuit.