Prepare the Cabinet

1.Open and remove, if applicable, the front and back doors of the cabinet. See the instructions provided with your cabinet.

2.Stabilize the cabinet by extending its anti-tip legs or bolting the cabinet securely to the floor.

See the instructions provided with your cabinet and read “4-Post Cabinet Requirements” on page 52.

The following illustration shows two anti-tip legs. Note that some cabinets have only one such leg.

3.Remove the side panels from the cabinet, if applicable.

See the instructions provided with your cabinet. Removing the side panels can improve access to the areas where you will install nuts and screws when securing the server in the cabinet.

10 Sun Fire V440 Server Installation Guide • July 2003

Image 18
Contents Sun Fire V440 Server Installation Guide Please Recycle Contents Setup and Power -On Procedures Background and ReferencePreface How This Book Is OrganizedUsing Unix Commands Typographic ConventionsSystem Prompts Related DocumentationAccessing Sun Documentation Contacting Sun Technical SupportSun Welcomes Your Comments Preparing for Installation About the Parts Shipped to YouVerify All Parts Verify that you have received all the parts of your systemPlan the Installation Transfer Online DocumentationWhat Next Installing a Sun Fire Server Into a 4-Post Cabinet Checklist of 4-Post Rackmounting Tasks Inventory for 4-Post Rackmounting Tools Required for Rackmounting Attach the Inner Glides to the Chassis Prepare the Cabinet Remove the side panels from the cabinet, if applicableLocate the Mounting Holes To use the Rack Alignment template, complete these steps Install the Slide Assemblies Sun Fire V440 Server Installation Guide July Installing a Sun Fire V440 Server Into a 4-Post Cabinet Install the Server Into the Cabinet Installing a Sun Fire V440 Server Into a 4-Post Cabinet Sun Fire V440 Server Installation Guide July What Next Install the Cable Management Arm Captive screw Slot Tab Mounting hole Inner glide Sun Fire V440 Server Installation Guide July Installing a Sun Fire V440 Server Into a 4-Post Cabinet Locate the speed pin on the end of the cable management arm Secure the Cords and Cables to the Cable Management Arm Upper lip Velcro straps Oval cutouts First section Oval cutouts Install Optional Components Install any optional components shipped with your systemConnecting the Cords and Cables Port InformationConnect the Power Cords to the Server PCI Choose a network port, using the following table as a guide Connect Twisted-Pair Ethernet CablesInstalling a Sun Fire V440 Server Into a 4-Post Cabinet Restore the Cabinet Setup and Power-On Procedures Set Up a System Console DeviceAbout Connecting the Server to a Terminal Server Terminal Straight-through cable Server Open a terminal session on the connecting device, and type Turn off power to the alphanumeric terminalHow to Access the System Console via tip Connection A terminal window on the other Sun system, type Prepare to Configure the Primary Network Interface Choose a host name for the server and make a note of itPower On the Server How to Power On via the Power Button How to Power On via the poweron Command Turn the system control keyswitch to the Locked positionPower button Standby Keyswitch Normal Locked Diagnostics At the Alom sc prompt, type the poweron command sc poweron Quickly enter the console command sc consoleSetup and Power-On Procedures What Next Background and Reference System LEDsFollowing table describes the power supply LEDs Serial Port Connector Serial Port Connector SignalsPost Cabinet Requirements Table A-44-Post Cabinet RequirementsTable A-44-Post Cabinet Requirements Sun Fire V440 Server Installation Guide July