3.With the help of an assistant, position one slide assembly on the inside of the cabinet with the front (short) mounting bracket at the front of the rack.

a.Use the holes you marked in Step 1.

b.Make sure that the slide assembly is level front-to-back.

4.Using two screws for each bracket, attach the front mounting bracket to the front rail of the cabinet and attach the back (long) mounting bracket to the back rail of the cabinet.

Count the rack rail holes to ensure that you are matching the holes used on the front rail.

To attach the slide assembly, use the appropriate screws for your type of rack:

Racks with mounting holes sized for U.S. dimensions require 10-32 screws.

Racks with mounting holes sized for metric dimensions require M4 or M6 screws.

a.Fully tighten the front bracket screws.

b.Partially tighten the back bracket screws.

Do not fully tighten the screws that attach the back brackets to the rack rails until after you slide the server into the cabinet.

c.Fully tighten the 8-32 lock nuts on the back mounting bracket.

Step 4b.

Step 4a.

Step 4c.

5. Repeat Step 3 and Step 4 for the other slide assembly.

14 Sun Fire V440 Server Installation Guide • July 2003

Image 22
Contents Sun Fire V440 Server Installation Guide Please Recycle Contents Setup and Power -On Procedures Background and ReferencePreface How This Book Is OrganizedUsing Unix Commands Typographic ConventionsSystem Prompts Related DocumentationContacting Sun Technical Support Accessing Sun DocumentationSun Welcomes Your Comments Preparing for Installation About the Parts Shipped to YouVerify All Parts Verify that you have received all the parts of your systemPlan the Installation Transfer Online DocumentationWhat Next Installing a Sun Fire Server Into a 4-Post Cabinet Checklist of 4-Post Rackmounting Tasks Inventory for 4-Post Rackmounting Tools Required for Rackmounting Attach the Inner Glides to the Chassis Prepare the Cabinet Remove the side panels from the cabinet, if applicableLocate the Mounting Holes To use the Rack Alignment template, complete these steps Install the Slide Assemblies Sun Fire V440 Server Installation Guide July Installing a Sun Fire V440 Server Into a 4-Post Cabinet Install the Server Into the Cabinet Installing a Sun Fire V440 Server Into a 4-Post Cabinet Sun Fire V440 Server Installation Guide July What Next Install the Cable Management Arm Captive screw Slot Tab Mounting hole Inner glide Sun Fire V440 Server Installation Guide July Installing a Sun Fire V440 Server Into a 4-Post Cabinet Locate the speed pin on the end of the cable management arm Secure the Cords and Cables to the Cable Management Arm Upper lip Velcro straps Oval cutouts First section Oval cutouts Install Optional Components Install any optional components shipped with your systemConnecting the Cords and Cables Port InformationConnect the Power Cords to the Server PCI Choose a network port, using the following table as a guide Connect Twisted-Pair Ethernet CablesInstalling a Sun Fire V440 Server Into a 4-Post Cabinet Restore the Cabinet Setup and Power-On Procedures Set Up a System Console DeviceAbout Connecting the Server to a Terminal Server Terminal Straight-through cable Server Open a terminal session on the connecting device, and type Turn off power to the alphanumeric terminalHow to Access the System Console via tip Connection A terminal window on the other Sun system, type Prepare to Configure the Primary Network Interface Choose a host name for the server and make a note of itPower On the Server How to Power On via the Power Button How to Power On via the poweron Command Turn the system control keyswitch to the Locked positionPower button Standby Keyswitch Normal Locked Diagnostics At the Alom sc prompt, type the poweron command sc poweron Quickly enter the console command sc consoleSetup and Power-On Procedures What Next Background and Reference System LEDsFollowing table describes the power supply LEDs Serial Port Connector Serial Port Connector SignalsPost Cabinet Requirements Table A-44-Post Cabinet RequirementsTable A-44-Post Cabinet Requirements Sun Fire V440 Server Installation Guide July