GE EPM 5350, EPM 5200, EPM 5300 Chapter Programming Quick Reference, Entering the Programming Mode

Page 89

CHAPTER 15: PROGRAMMING QUICK REFERENCE

CHAPTER 15

PROGRAMMING QUICK REFERENCE

15.1: Entering the Programming Mode

1.Hold PHASE/NEXT key and press AMPS key.

2.Display blanks and shows either a ‘0’, ‘1’, or ‘3’.

3.If ‘3’ is not displayed then press AMPS key until ‘3’ is displayed.

4.Release AMPS key and press PHASE/NEXT key, while ‘3’ is still displayed.

5.Display shows ‘333’ momentarily.

6.Upper display starts counting. Press PHASE/NEXT key when ‘5’ is displayed to register the ‘5’.

7.Repeat step 6 until ‘555’ has been registered.

15.2: Data Entry Sequence

1.At programmable numerical fields or Switch Pack fields, Press AMPS key to begin Data Entry Sequence.

2.The current setting moves to middle row of display and dashes appear in the bottom row. Press VOLTS key to toggle between available choices.

3.When a correct choice is selected, press AMPS key to store.

15.3: Programming Groups

Programming

Description

groups

 

 

 

0

Global Meter Setup—Integration Interval, Meter Address,

 

Communication Setting, Relay Settings

 

 

1

Full Scale Settings. Voltage Full Scale, Current Full Scale and Power

 

Function Full Scale.

 

 

2

Meter Calibration

 

 

3

Calibration Ratios

 

 

4

Volts and Current Limits

 

 

5

Power Function Limits

 

 

6

THD Limits

 

 

7

Imbalance Reversal Limits

 

 

8

DC Output Calibration

 

 

GE Industrial Systems

5300P Advanced Power Meter

85

Image 89
Contents EPM 5200, 5300 Digital Multifunction Power MonitorsPage Table of Contents REFERENCE………………81 SET LIMITS/RELAYSMode Single Phase System Chapter AC Power MeasurementRelationship between apparent, real Reactive power Three-Phase SystemPoly Phase System 1 Delta, 2 Wye Consumption, Demand and Poor Power FactorTotal Harmonic Distortion THD Waveform and HarmonicsSinusoidal Waveform a sin ω ⋅ t Diagram 2.1 Standard installation Chapter Mechanical InstallationPort Connecting the Current Circuit Chapter Electrical InstallationCT Connection Helpful Debugging ToolsConnection to the Main Power Supply Connecting the Voltage CircuitElectrical Connection Installation Control Power Option Suffix CurrentList of Connection Diagrams 2L1 Three Phase Four-Wire Wye with CT and PTs IV. Three-Phase Four-Wire Wye with Direct Voltage and CTsLine Back View LoadEPM 5300P-S VI. Single Phase with CT and PT ConnectionVIII. Three-Phase Four-Wire WYE with 2.5 Element VII. Dual-Phase with CTs and PTsRelays & 1 KYZ Pulse Output -NL Option Relay, Protection and Pulse OutputEPM 5300P Relay Overview Standard Rate Table for Watts Decimal Point Placement Change in Level KW/MWKYZ Pulse Outputs NL2 Option VoltageKYZ Relay Connection for -NL2 Option 9999.0 Units W Hour 999.9 99.99RS-232C Chapter Communication InstallationRS-485 Connection for DB-9 FemaleRS-485 Hookup Diagram 2 wire Half Duplex RS-485 Hookup Diagram 2 wire Half Duplex Closed Loop RS-485 Hookup Diagram 2 wire Half Duplex Detail View RS-485 Hookup Diagram 4 wire Full Duplex Bottom View Shown RS-485 Hookup Diagram 4 wire Full Duplex Detail ViewComputer Network of Instruments and Long Distance CommunicationProgramming the Modem Modem Connected to Computer Originate ModemDebugging Communication Problems Communication Installation Chapter Overview Power A, B, CAccessing %THD Functions Accessing the Power FunctionsAccessing Voltage and Current Phases Step Viewing Individual Phase Indication for Power FunctionsResetting Values Protected Reset Unprotected ResetAccessing the LM1/LM2 Set Limits Resetting Hour ReadingsPhase Reversal Phase Imbalance Voltage Phase Reversal and ImbalanceThis display Press and hold down Indicates a VoltageAppears, confirming a successful print command Access ModesPrint Operating Data Press and hold Press Amps until a AppearsPrint Programming Data Accessing Firmware Version/LED TestStep Press and hold PHASE/NEXT Press Amps until 4 appears Step Switch Packs General ProcedureChapter Programming Overview Groups Functions PacksStandard Numeric Data Entry Programming Mode Data EntryEPM 5200P Chapter5300P 5200P 5350P Feature 5300P 5200P 5350PEPM 5300P vs. EPM 5200P vs. EPM 5350P Checksum Error-Protective Self-Checking Algorithms Chapter Entering Programming ModePassword Entry Entering Programming ModeEntering Programming Mode Group 0, Function 0-The Integration Interval Chapter Programming Group 0 Global Meter SetupFunction FunctionGroup 0, Function 1-The Meter Address Group 0, Function 2-BAUD Rate Group Function Pack Group 0, Function 3-System ConfigurationDown +PF Pack Switch Feature Segment PositionModbus Plus Capability Open Delta System Installation ProgrammingPrinting Option Disabling PreventsTo change the System Configuration Switch Settings Group 0, Function 3-Programming ProcedureSwitch Description Relay ModeSwitch C Description Definitions04.P Controls Relay 05.P Controls Relay 2 and 3 if NL4 Programming StepsGroup 0-FUNCTION Number Description To change the Relay Mode to either Fail-safe or Reset Group and Function Number Description To program Relay To change Time DelaysParameter Description Group 0, Function 6-KYZ Parameter Selection06P Selection KYZ Pulse KYZ Pulse ValueValue PER PER Watt Hour FSW=9.999Situation 4 FSW=9.999 Situation 3 FSW=99.99Standard Factory SET-UP is THREE-PHASE FOUR-WIRE Group 0, Function 7-Number of PhasesGroup and Function Number FormulasVoltage Full Scale To change the Full Scale SettingsPress Volts to move decimal point Press Amps to store CT T YPE Full Scale Group 1, Function 1-Amperage Full ScaleStep Press Amps to begin Data Entry Sequence Example 2 480/120 PT, 1000/5 CT FSV=480 FSA=1000 a FSW one phase=480 V ⋅ 1000 aExample 3 14.4 KV/120, 1000/5 CT FSV=14.40 KV FSA=1000 aTo change the scale factor setting for wattage Programming Group Calibration Requirements Chapter Programming Group 2-METER CalibrationHigh End Calibration-Volts AN, BN, CN High End Calibration-Amps A, B, CTo change the calibration high end-Functions 0 Voltage Range Input Source Group 2 ValueFor Amps Low End Function Press MAX/MIN/LIMITS to end calibration procedure Chapter Groups 4, 5 and 6-SET Limits and Relays Time Delays & Relay ModeExample of LM1/LM2 SET Limits Trip RelayGroup 4 Programming Format for Limit Condition Group 4, Functions 0-3-LM1/LM2 Set LimitsGroup 5, Functions 0-7-LM1/LM2 Set Limits Digit Up Digit Down 0120 There are 3 Switches to SET with LimitsProgramming Group 6, LM1/LM2 Set Limits LM1 LM2 Switch Value LED ABOVE/BELOW RelayLM1 LED LM2 LED Switch Level ABOVE/BELOW Relay Limits or Relays Programming ProcedureDigit Up Digit Down 012.0 Digit Down Digit Up 009.0Follow this step for Disabling Limits Press Amps once to Disable the LimitSee to Exit ∃TRIP Relay 1 %TRIP Relay 2 &LEVEL ∋ENABLE/DISABLE Phase Reversal and Phase ImbalanceVoltage Phase Reversal Detection Group 7, Function 0-Voltage Phase Reversal DetectionVoltage Phase Imbalance To change the phase reversal settingTo change the percentage voltage phase imbalance Group 7, Function 1-Percentage Voltage Phase ImbalanceSee to Exit Chapter Exiting Programming Mode Exiting Programming Mode Chapter Programming Quick Reference Entering the Programming ModeData Entry Sequence Programming GroupsReserved Switches Group 0-Global Meter SetupGroup 2 Calibration Group 1 Full Scale SetupGroup 3 Calibration Ratios Group 4 Volt/Current LimitsGroup 6 THD Limits Group 5 Power Function LimitsGroup 7 Imbalance/Reversal Limits Group 8 DC output CalibrationKEY Designations Programming Quick Reference Ethernet Module Chapter Ethernet OptionDescription LED Functions Ethernet Option SetupSetting the IP Address Default IP AddressNetwork Port Login AutoIPTelnet to Port Network ConfigurationARP on Windows Baud Rate Configuration ParametersGE Multilin
Related manuals
Manual 134 pages 15.43 Kb