5.1.3.2 Sequential startup
It is possible to delay outlet
Controlled outlet startup after a given time is based on startup of the main outlet.
5.2The different server and UPS shutdown sequences
5.2.1Extended power outage, shutdown initiated by the Shutdown Timer (Shutdown after)
During battery backup time, the Shutdown Timer of the Network Management Card is reached: After a
Shutdown duration: Maximum value of shutdown times of protection application subscribed to the card. This value is updated each time a client subscribes/ unsubscribes.
Utility failure | Start shutdown | Start shutdown main | Utility restore |
output 1 | output | ||
Utility |
|
|
|
Main output |
|
|
|
| Shutdown after: | Shutdown duration |
|
| main output |
| |
|
|
| |
NSM 1 on main |
|
|
|
output |
|
|
|
| Shutdown after 1: |
|
|
Output 1 |
|
|
|
| Shutdown |
| |
| duration output 1 |
| |
NSM 2 on output 1 |
|
|
|
5.2.2Extended power outage, shutdown initiated by the "Low battery power" message
When the "Low battery power" criterion is displayed, the UPS is shut off after taking into account the shutdown duration of the servers.
"Low battery power": The message appears if either of the two following criteria is checked:
-Low Battery Level
-Low Battery Delay
Network Management Card – User Manual | 34003991EN/EB | Page 69/118 |