Operation: Operation Procedures
How to return to normal operation
Set the DC DISCONNECT switch on all of the XR Battery enclosures and the
Set the Q1 switch on the
Set the Q5 switch on the
Set the SYSTEM ENABLE switch on the UPS to the ON position.
Note: Wait approximately 30 seconds for system to start.
Using the display interface, select the following:
| UPS | Press | |
| Alarms |
| |
| Power Dist | Log |
|
| Switch Gear | Admin |
|
| Environment | Help |
|
| Turn UPS On | Press | |
|
|
| |
| UPS On Into Bypass |
|
UPS Control
UPS Status
UPS Tests & Diags
UPS Configuration
UPS Load is ON.
Press
Press
Symmetra PX 160 kW 400 V Operation | 11 |