4.0 Installation

CAUTION: The GBC Voyager 3 can only be installed by a trained GBC Service Representative.

Before a Voayger 3 Laminator can be installed, there are a few requirements that must be met. Make cer- tain that each of the requirements listed in the fol- lowing pre-installation checklist are met prior to installation.

CAUTION: Failure to follow the pre-installa- tion check list can result in damage to the laminator.

As a customer, you are responsible for ensuring the crates are uncrated and the components are set in proper position as illustrated in Figure 4.1.1 Suggested Floor Layout. The installation time is out- lined to allow for maximum hands on training with the operators.

4.1 Pre-installation

Are the doorways and hallways wide enough for the laminator to be moved to the installa- tion site?

Is there ample room for the laminator? The laminator occupies 16 ft. by 6 ft. of floor space (488 cm x 183 cm).

A safe work area constitutes enough room to work with the materials at hand while being free to move around the laminator without interference from the laminator. You must allow a minimum of 5 ft. (152 cm) in front of the feeder and on the operator side, and a minimum of 2 ft. (61 cm) behind the stacker and drive side of the laminator. Refer to Figure 4.1.1 Floor layout.

Is the environment appropriate for the laminator? A controlled environment is recom- mended.

CAUTION: The operating environment must be free of dust, flammable liquids and vapors.

The laminator requires a clean, dust and vapor free environment to operate properly.

2004 General Binding Corporation

Page 4-1

Image 25
Contents Voyager Page Voyager General Binding Corporation III General Binding Corporation Explanation of symbols SafetyGeneral rules of safety Following actions can result in machine damage Jog/Slow Speed w/Guard Open Safety shieldsEmergency stops E-Stop Heat PneumaticsSafety labels Voyager Sharp Edge Main Power SwitchGBC Films Group Over view Feeder Know your laminatorLaminator Separator Voyager Limited 90-Day Warranty Voyager Specifications Feeder Specifications Feeder Air Pump Specifications Heater Power Requirement Power supplied by the laminatorPre-installation InstallationTo .1.2 connections Water supply drop Installation Receiving the crates Uncrating Laminator Positioning the componentsStacker table Vacuum/ pump ConveyorWater heater/ reservoir tank 1 Component placement Safety Checklist Voyager