Startup

9.2Starting the XDF

The XDF is started, stopped and controlled with Liebert’s iCOM controller. Figure 28 shows the iCOM keypad.

Figure 28 iCOM controller keys

 

Alarm Key

 

Up Arrow Key

 

 

?

 

 

 

On/Off Key

Help Key

Left Arrow Key

Enter Key

Right Arrow Key

 

ESC

 

 

 

 

Escape Key

 

Down Arrow Key

 

To start the XDF:

1.Press the On/Off key on the iCOM controller.

2.Confirm internal airflow: Inside enclosure, (evaporator fan discharge).

3.Confirm cooling air begins circulating.

4.Power up the UPS (if provided).

5.Close the XDF’s doors, if open.

NOTE

Control requires 30-60 seconds to boot up after the 120V power is supplied.

38

Image 44
Contents Liebert XDF Page Table of Contents Piping CONSIDERATIONS-WATER/GLYCOLMODELS only Filling the XDF with COOLANT-WATER or GlycolElectrical Connections Cable Management OptionsMaintenance SpecificationsTables Important Safety Instructions Glossary of Symbols Indicates weightHazardous Voltage Present Indicates ground connectionCondenser Coil 1 Backup Ventilation Air Intake CompressorEntry Point Condenser Air ICOM Controller Operational Overview Water/Glycol Cooled Model Brazed Plate Condenser behind grille ICOM ControllerCondenser fan Removable to reduceHeight temporarily Return Line FemaleDimensional data, self-contained, air cooled model 139.7mm 176.5mm47.6mm Plate Connection114mm EntryCutouts Cable Entry CutoutXDF Components FrameEnclosure DoorsHeat Removal-Water/Glycol Cooled XDF Environmental ControlHeat Removal-Self-Contained, Air Cooled XDF Brazed Plate Condenser FrontRear Control-Liebert’s iCOM Controller Liebert iCOM controllerCoolant Source-Water/Glycol Models Closed-Loop Water SystemDrycooler Loop Water/Glycol Return Line CooledPower Options MP Advanced Power Strips and Controllers Uninterruptible Power SupplyOptional Equipment General Enclosure OptionsRecommended Setup Equipment InstallationInspection Unloading the XDFFork Lift Handling the Unit While It is PackagedUnpack the XDF Removing the XDF from Skid Right front corner detail controls side of XDFRoll XDF off the shipping skid 915mm XDF Site Preparation36 915mm Voltage Requirements Voltage Input RequirementsDrycooler Installation-Water/Glycol Cooled Model Optional condensate pump performanceMaximum Head Model Feet m 60Hz 50HzEquipment Layout Recommended equipment arrangementFrame and Enclosure Configurations Mounting HardwareInternal Mounting Rails Rear-Mount Rails-PositionDoor-Remove Side Panels-Remove and ReplaceRemove the Door Quick Door RemovalRemove the Right Panel Replace a PanelGeneral Closed Loop Water SystemPiping CONSIDERATIONS-WATER/GLYCOL Models only Water supply flow ratesFreeze Protection-Coolant Type and Insulation Expansion Tanks, Fluid Relief Valves and Other DevicesCorrosion Protection Glycol Solutions Drycooler Loop SystemEthylene glycol concentrations Glycol supply flow ratesXDF Water/Glycol Cooled Unit Volume Volume in standard Type L copper pipingPreparing the System for Filling Filling the XDF with COOLANT-WATER or GlycolDashed line delineates equipment compartment Electrical ConnectionsCustomer Cable Entry Points Rear Utility Power Supply Route Input Power Cables Through the XDF’s TopCable Management Options Cable Management ConsiderationsCable Management Top Cover and Back Cable AccessOptional Cable Management Channel Cable Tray Detail View Site Conditions XDF Startup Inspection ChecklistStartup Starting the XDF Escape Key Down Arrow KeyOperation Environmental ControlICOM Components and Functions Keyboard icons and functions Icon Key Name FunctionNavigating Through the iCOM Display OK noAccessing Menus and Settings Viewing Data Entering the PasswordChanging Operational Settings User menu icons Icon Name DescriptionHighlight the setting to be changed by pressing Enter Changing iCOM’s Display SettingsChanging the XDF’s Default Operating Temperature Operation With the Door Open XDF Compressor Backup Ventilation SystemUninterruptible Power Supply Troubleshooting Periodic MaintenanceMaintenance Specifications Physical specificationsSelf- Contained Water/Glycol Dimensions Air Cooled XDF MonitoringSelf- Contained Water/Glycol Electrical Data Air Cooled XDF Electrical specificationsTotal heat rejection Optional Power Systems UPS performance dataRemote Monitoring Only MP Advanced Power Strip specificationsTypes Quan Port Remote Monitoring and Control Page Ne t ItiTi n That