Maytag MDG-75 installation manual Single-Phase 1Ø Electrical Connections Leads

Page 26

Actual electrical wire connections are made to the L1 and L2 terminals of the motor contactor located in the rear service box mentioned above. The ground connection is also made to the copper lug also provided in this box.

Single-Phase (1Ø) Electrical Connections Leads

Black

White

Green

+

+

+

Positive

Neutral

Ground

 

or

 

 

L2

 

If local codes permit, power to the dryer can be made by the use of a flexible U.L. listed power cord/ pigtail (wire size must conform to rating of dryer), or the dryer can be hard wired directly to the service breaker panel. In both cases, a strain relief must be installed where the wiring enters the dryer.

2) 3-Phase (3ø) Wiring Connections or Hookup (for Non-Reversing Models Only)

The electrical connections on ALL 3-phase (3ø) gas dryers are made into the rear service box located at the upper left area of the dryer.

NOTE: A CIRCUIT SERVICING EACH DRYER MUST BE PROVIDED.

If local codes permit, power to a gas dryer can be made by the use of a flexible U.L. listed power cord/pigtail (wire size must conform to rating of dryer), or the dryer can be hard wired directly to the service breaker panel. In ALL cases, a strain relief must be installed where the wiring enters the dryer.

22

Image 26
Contents MDG-75 Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Routine Maintenance Section Important InformationSafety Precautions What to do if YOU Smell GASPage SPECIFICATIONS/COMPONENT Identification SpecificationsSpecifications Component Identification Page Installation Procedures Location RequirementsUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Horizontal VentingSingle Dryer Venting Page Page Page Electrical Information Electrical RequirementsMDG-75 Gas Page Single-Phase 1Ø Electrical Connections Leads Page Page GAS Information Type of GAS Page Page Preparation for OPERATION/START-UP Preoperational Tests Basket Coating Preoperational Instructions Shut Down Instructions Parts SERVICE/PARTS InformationService Warranty Information Returning Warranty CardsRoutine Maintenance CleaningAdjustments LubricationProcedure for Functional Check Replacement Components Page Page Reversing Timer SPIN/DWELL Adjustments Timing LegendData Label Information Data LabelSerial Number Troubleshooting Microprocessor Controller Computer ModelsBlower and fan motors are not operating does not start Failed microprocessor controller computer Failed keyboard touch pad label assembly Microprocessor controller computer L.E.D. display reads Sefl Dryer operates but is taking too long to dry GAS Models AA. Condensation on main door glass Timer Models Blower/fan motors are not operating does not start GAS Models Dryer operates but is taking too long to dry Condensation on main door glass Page Manual Reset HI-LIMIT Instructions P O RTA N T