Frigidaire 137111500B Gas supply requirements, Exhaust system requirements

Page 4

Gas supply requirements

- EXPLOSION HAZARD - Uncoated copper tubing will corrode when subjected to natural gas, causing gas leaks. Use ONLY black iron, stainless steel, or plastic-coat- ed brass piping for gas supply.

1.Installation MUST conform with local codes, or in the absence of local codes, with the National Fuel Gas Code, ANSI Z223.1 (latest edition).

2.The gas supply line should be 1/2 inch (1.27 cm) pipe.

3.If codes allow, flexible metal tubing may be used to connect your dryer to the gas supply line. The tubing MUST be constructed of stainless steel or plastic-coated brass.

4.The gas supply line MUST have an individual shutoff valve.

5.A 1/8 inch (0.32 cm) N.P.T. plugged tapping, accessible for test gauge connection, MUST be installed immediately upstream of the gas supply connection to the dryer.

6.The dryer MUST be disconnected from the gas supply piping system during any pressure testing of the gas supply piping system at test pressures in excess of 1/2 psig (3.45 kPa).

7.The dryer MUST be isolated from the gas supply piping system during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 psig (3.45 kPa).

8.Connections for the gas supply must comply with the Standard for Connectors for Gas Appliances, ANSI Z21.24.

Exhaust system requirements

Use only 4 inch (10.2 cm) diameter (minimum) rigid or flexible metal duct and approved vent hood which has a swing-out damper(s) that open when the dryer is in operation. When the dryer stops, the dampers automatically close to prevent drafts and the entrance of insects and rodents. To avoid restricting the outlet, maintain a minimum of 12 inches (30.5 cm) clearance between the vent hood and the ground or any other obstruction.

- FIRE HAZARD - Failure to follow these in- structions can create excessive drying times and fire hazards.

The following are specific requirements for proper and safe operation of your dryer.

- FIRE HAZARD - Do not install a clothes dryer with flexible plastic or metal foil venting materials. Flexible venting materials are known to collapse, be easily crushed and trap lint. These conditions will obstruct clothes dryer airflow and increase the risk of fire.

If your present system is made up of plastic duct or metal foil duct, replace it with a rigid or semi-rigid metal duct. Also, ensure the present duct is free of any lint prior to installing dryer duct.

Correct

Correct

Incorrect

Incorrect

4

Image 4
Contents Installation Instructions Table of Contents Electrical requirements for electric dryer Electrical requirements for gas dryerGas supply requirements Exhaust system requirementsExhaust system requirements Manufactured or mobile home installation Exhaust directionDo not Install Your Dryer Clearance requirementsInstalled dryer dimensions Grounding requirements Electric dryer USA Electrical installationGrounding requirements Electric dryer Canada Grounding requirements Gas dryer USA and Canada Gas connectionElectrical connection non-Canada 3 wire cord Turn off power supply to outletElectrical connection non-Canada 4 wire cord General installation Window Door Reversal Instructions Page Accessories Replacement parts 1-800-944-9044 in CanadaÍndice Requisitos eléctricos de la secadora eléctrica Requisitos eléctricos de la secadora a gasRequerimientos del suministro de gas Requisitos del sistema de escapeRequisitos del sistema de escape continuación Longitud MáximaInstalación en una casa rodante Dirección del escapeRequisitos de despeje No Instale LA SecadoraDimensiones de la secadora instalada Instalación eléctrica Requisitos de conexión a tierra secadora eléctrica CanadáConexión de gas Flujo DE GASConexión eléctrica fuera de Canadá trifilar Tornillo VerdeConexión eléctrica fuera de Canadá tetrafilar Instalación general Conecte el tubo de escape al sistema de escape exteriorPage Page Accesorios Piezas de repuesto 1-800-944-9044 en Canada