It is suggested that the ductwork from each dryer not exceed 20 feet (6.09 meters) with no more than two

(2)elbows (excluding dryer connections). If the ductwork exceeds 20 feet (6.09 meters) or has numerous elbows, the cross-sectional area of the ductwork must be increased in proportion to the length and number of elbows in it. In calculating duct size, the cross-sectional area of a square or rectangular duct must be increased twenty percent (20%) for each additional 20 feet (6.09 meters). The diameter of a round exhaust duct should be increased ten percent (10%) for each additional 15 feet (4.57 meters). Each 90º elbow is equivalent to an additional 40 feet (12.19 meters), and each 45º elbow is equivalent to an additional 20 feet (6.09 meters).

IMPORTANT: For extended ductwork runs, the cross section area of the ductwork can only be increased to an extent. Maximum proportional ductwork runs cannot exceed 20 feet (6.09 meters) more than the original limitations of 20 feet (6.09 meters) with two (2) elbows. When the ductwork approaches the maximum limits as noted in this manual, a professional heating, ventilating, and air-conditioning (HVAC) firm should be consulted for proper venting information.

ALL ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the ductwork.

17

Image 21
Contents AD-170SE Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check Receiving and Handling Important InformationWhat to do if YOU Smell GAS Safety PrecautionsStandards Specifications SPECIFICATIONS/COMPONENT IdentificationSpecifications Gas and Steam Component Identification Page Location Requirements Installation ProceduresUNPACKING/SETTING UP Page Dryer Enclosure Requirements Fresh AIR Supply Requirements General Exhaust Ductwork Information Exhaust RequirementsAnywhere Downstream of the Dryer Page Page Page Page Electrical Information GAS and Steam Page Page GAS Information Type of GAS Page Page Steam Information Operating Steam PressureSteam Damper System Compressed Air Supply Air Pressure Page Preparation for OPERATION/START-UP Preoperational Test Basket Tumbler Coating Compressed AIR Requirements Preoperational InstructionsShutdown Instructions SERVICE/PARTS Information ServiceParts Returning Warranty Cards Warranty InformationWarranty Returning Warranty PartsPage Cleaning Routine MaintenanceSteam Dryers Lubrication AdjustmentsManual Reset Burner HI-LIMIT Instructions PhaseDual Timer Data Label Information Timing Legend Reversing Timer SPIN/DWELLADJUSTMENTSProcedure for Functional Check Replacement Components Page Sensoractivated Fire Extinguishing S.A.F.E. System InstallationTypical water supply Optional Manual Bypass System Reset NON-COIN S.A.F.E. System Check ProcedureF.E. System Theory of Operation Page ADC Part No 12 01/23/09