J. PREOPERATIONAL TEST

ALL dryers are thoroughly tested and inspected before leaving the factory. However, a preoperational test should be performed before the dryer is publicly used. It is possible that adjustments have changed in transit or due to marginal location (installation) conditions.

1.Turn on electric power to the dryer.

2.Make sure the main door is closed and the lint drawer is securely in place.

3.Refer to the Operating Instructions for starting your particular model dryer.

4.Check to ensure that the basket (tumbler) starts in the clockwise (CW) direction. Additionally, check the direction of the blower motor impellor (fan) to ensure that the blower motor impellor (fan) rotates in the clockwise (CW) direction as viewed from the front. If it is, the phasing is correct. If the phasing is incorrect, reverse two (2) of the leads at L1, L2, or L3 of the power supply connections made to the dryer.

IMPORTANT: Dryer blower motor/pulley that drives the impellor/fan (squirrel cage) when viewed from the back of the dryer must turn in the counterclockwise (CCW) direction, otherwise the dryer efficiency will be drastically reduced and premature component failure can result.

5.Heat Circuit Operational Test a. Gas Models

1)When the dryer is first started (during initial start-up), the burner has a tendency not to ignite on the first attempt. This is because the gas supply piping is filled with air, so it may take a few minutes for this air to be purged from the lines.

2)The dryer is equipped with a Direct Spark Ignition (DSI) system, which has internal diagnostics. If ignition is not established after three (3) attempts, the heat circuit DSI module will LOCKOUT until

it is manually reset. To reset the DSI system, open and close the main door and restart the dryer (press the “START” key).

NOTE: During the purging period, check to be sure that ALL gas shutoff valves are open.

3)Once ignition is established, a gas pressure test should be taken at the gas valve pressure tap of each dryer to assure that the water column (W.C.) pressure is correct and consistent.

NOTE: Water column pressure requirements (measured at the gas valve pressure tap)...

Natural Gas --------------------- 3.5 Inches (8.7 mb) Water Column.

Liquid Propane (L.P.) Gas --- 10.5 Inches (26.1 mb) Water Column.

34

Image 38
Contents AD-170SE Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check Important Information Receiving and HandlingSafety Precautions What to do if YOU Smell GASStandards SPECIFICATIONS/COMPONENT Identification SpecificationsSpecifications Gas and Steam Component Identification Page Installation Procedures Location RequirementsUNPACKING/SETTING UP Page Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements General Exhaust Ductwork InformationAnywhere Downstream of the Dryer Page Page Page Page Electrical Information GAS and Steam Page Page GAS Information Type of GAS Page Page Operating Steam Pressure Steam InformationSteam Damper System Compressed Air Supply Air Pressure Page Preparation for OPERATION/START-UP Preoperational Test Basket Tumbler Coating Preoperational Instructions Compressed AIR RequirementsShutdown Instructions Parts SERVICE/PARTS InformationService Warranty Warranty InformationReturning Warranty Cards Returning Warranty PartsPage Routine Maintenance CleaningSteam Dryers Adjustments LubricationDual Timer Manual Reset Burner HI-LIMIT InstructionsPhase Data Label Information Reversing Timer SPIN/DWELLADJUSTMENTS Timing LegendProcedure for Functional Check Replacement Components Page Installation Sensoractivated Fire Extinguishing S.A.F.E. SystemTypical water supply Optional Manual Bypass F.E. System Theory of Operation System ResetNON-COIN S.A.F.E. System Check Procedure Page ADC Part No 12 01/23/09