NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (all the way around). The duct must be centered within this opening.

a.Outside Ductwork Protection

1)To protect the outside end of the horizontal ductwork from the weather, a 90° elbow bent downward should be installed where the exhaust exits the building. If the ductwork travels vertically up through the roof, it should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and the nearest obstruction.

IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

3.Multiple Dryer (Common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a “common main duct.” The individual ducts should enter the bottom or side of the main duct at an angle not more than 45° in the direction of the flow and should be spaced at least 55-3/4” (141.61 cm) apart. The main duct should be tapered, with the diameter increasing before each individual 18-inch (45.72 cm) duct is added.

IMPORTANT: The dryer is not provided with a back draft damper. When exhausted into a multiple (common) exhaust line, a back draft damper must be installed at each dryer duct.

IMPORTANT: No more than three (3) dryers should be connected to one (1) main common duct.

The main duct may be any shape or cross-sectional area, so long as the minimum cross section area is provided. The illustrations on page 20 show the minimum cross section area for multiple dryer round or square venting. These figures must be increased 10 square inches (64.52 square centimeters) when rectangular main ducting is used, and the ratio of duct width to depth should not be greater than 3-1/2 to

1.These figures must be increased in proportion if the main duct run to the last dryer to where it exhausts to the outdoors is unusually long (over 20 feet [6.09 meters]) or has numerous elbows (more than two [2]) in it. In calculating ductwork size, the cross-sectional area of a square or rectangular duct must be increased twenty percent (20%) for each additional 20 feet (6.09 meters). The diameter of a round exhaust must be increased ten percent (10%) for each additional 20 feet (6.09 meters). Each 90° elbow is equivalent to an additional 40 feet (12.19 meters) and each 45° elbow is equivalent to an additional 20 feet (6.09 meters).

IMPORTANT: For extended ductwork runs, the cross section area of the ductwork can only be increased to an extent. Maximum proportional ductwork runs cannot exceed 20 feet (6.09 meters) more than the original limitations of 20 feet (6.09 meters) with two (2) elbows. When the ductwork approaches the maximum limits as noted in this manual, a professional heating, ventilating, and air-conditioning (HVAC) firm should be consulted for proper venting information.

IMPORTANT: Exhaust back pressure measured by a manometer in the exhaust duct must be no less than 0 and must not exceed 0.3 inches (0.74 mb) of water column (W.C.).

18

Image 22
Contents AD-170SE Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check Important Information Receiving and HandlingSafety Precautions What to do if YOU Smell GASStandards SPECIFICATIONS/COMPONENT Identification SpecificationsSpecifications Gas and Steam Component Identification Page Installation Procedures Location RequirementsUNPACKING/SETTING UP Page Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements General Exhaust Ductwork InformationAnywhere Downstream of the Dryer Page Page Page Page Electrical Information GAS and Steam Page Page GAS Information Type of GAS Page Page Operating Steam Pressure Steam InformationSteam Damper System Compressed Air Supply Air Pressure Page Preparation for OPERATION/START-UP Preoperational Test Basket Tumbler Coating Preoperational Instructions Compressed AIR RequirementsShutdown Instructions Service SERVICE/PARTS InformationParts Warranty Warranty InformationReturning Warranty Cards Returning Warranty PartsPage Routine Maintenance CleaningSteam Dryers Adjustments LubricationPhase Manual Reset Burner HI-LIMIT InstructionsDual Timer Data Label Information Reversing Timer SPIN/DWELLADJUSTMENTS Timing LegendProcedure for Functional Check Replacement Components Page Installation Sensoractivated Fire Extinguishing S.A.F.E. SystemTypical water supply Optional Manual Bypass NON-COIN S.A.F.E. System Check Procedure System ResetF.E. System Theory of Operation Page ADC Part No 12 01/23/09