I. PREPARATION FOR OPERATION/START-UP

The following items should be checked before attempting to operate the dryer:

1.Read ALLCAUTION,” “WARNING,” and “DIRECTION” labels attached to the dryer.

2.Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label. In the case of 208 VAC or 230/240 VAC, the supply voltage must match the electric service exactly.

3.GAS MODELS - Check to ensure that the dryer is connected to the type of heat/gas indicated on the dryer data label.

4.GAS AND ELECTRIC MODELS - The sail switch damper assembly was installed and adjusted at the factory prior to shipping. However, each sail switch adjustment must be checked to ensure that this important safety control is functioning. (refer to Sail Switch Adjustment on page 33).

5.GAS MODELS - Be sure that ALL gas shutoff valves are in the open position.

6.Be sure ALL side and base panels are on the dryer.

7.Check ALL service doors to ensure that they are closed and secure.

8.Be sure the lint drawer is securely in place.

9.Rotate the basket (tumbler/drum) by hand to be sure it moves freely.

10.Check bolts, nuts, screws, terminals, and fittings for security.

11.STEAM MODELS - Check to ensure air supply (80 psi [5.51 bar]) is connected to the dryers.

12.STEAM MODELS - Check to ensure ALL steam shutoff valves are open.

13.STEAM MODELS - Check steam damper operation.

14.Check basket (tumbler) bearing setscrews to ensure they are ALL tight.

31

Image 35
Contents ML-75V Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check of Replacement Section Safety PrecautionsStandards Specifications SPECIFICATIONS/COMPONENT IdentificationSpecifications Component Identification Page Location Requirements Installation ProceduresUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Requirements General Exhaust Ductwork Information Exhaust RequirementsOutside Ductwork Protection Page Page Page Electrical Requirements Electrical InformationGas and Steam Models Only Page Single-Phase Electrical Lead Connections Page GAS Information Type of GAS Page Page Steam Information Operating Steam PressurePage Compressed Air Supply Air Pressure Page Preparation for OPERATION/START-UP Preoperational Tests Basket Tumbler Coating Preoperational Instructions Coin Models NON-COIN Models Shutdown Instructions Dual Timer DryersReversing Timer SPIN/DWELL Adjustments Parts SERVICE/PARTS InformationService Returning Warranty Parts Warranty InformationReturning Warranty Cards WarrantyPage Cleaning Routine MaintenanceLubrication AdjustmentsProcedure for Functional Check Replacement Components Page Data Label Information Serial Number Dual Timer Manual Reset Burner HI-LIMIT InstructionsPhase Fire Suppression System F.S.S S. In ActionBefore YOU Start Check Local Codes and Permits InstallationTypical water supply Optional Manual Bypass S. Theory of Operation S. Water Valve Check Starting a Cycle When Computer is in F.S.S. is Disabled Mode ADC Part No 05/26/05