3.Multiple Dryer (Common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a “common main duct.” The individual ducts should enter the bottom or side of the main duct at an angle not more than 45º in the direction of airflow and should be spaced at least 38-5/16” (97.31 cm) apart. The main duct should be tapered, with the diameter increasing before each individual duct (10-inch [25.4 cm] minimum) is added.

IMPORTANT: No more than four (4) dryers should be connected to main common duct.

The main duct may be any shape as long as the minimum cross section area is provided. The illustrations on page 17 show the minimum cross section area for multiple dryer round or square venting. These figures must be increased 10 square inches (64.52 square centimeters) when rectangular main ducting is used, and the ratio of duct width to depth should not be greater than 3-1/2 to 1. These figures must be increased in proportion if the main duct run from the last dryer to where it exhausts to the outdoors is unusually long (over 15 feet [4.6 meters]) or has numerous (more than two [2] elbows in it). In calculating ductwork size, the cross section area of a square or rectangular duct must be increased twenty percent (20%) for each additional 15 feet (4.6 meters). The diameter of a round exhaust must be increased ten percent (10%) for each additional 15 feet (4.6 meters). Each 90º elbow is equivalent to an additional 30 feet (9.14 meters) and each 45º elbow is equivalent to an additional 15 feet (4.6 meters).

IMPORTANT: For extended ductwork runs, the cross section area of the ductwork can only be increased to an extent. Maximum proportional ductwork runs cannot exceed 15 feet (4.6 meters) with two (2) elbows. When the ductwork approaches the maximum limits as noted in this manual, a professional heating, ventilating, and air-conditioning (HVAC) firm should be consulted for proper venting information.

The ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the ductwork.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (2.54 cm) larger than the duct (all the way around). The duct must be centered within this opening.

Outside Ductwork Protection

To protect the outside end of the horizontal ductwork from weather, a 90º elbow bent downward should be installed where the exhaust exits the building. If the ductwork travels vertically up through the roof, it should be protected from the weather by using a 180º turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and the nearest obstruction.

IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

16

Image 20
Contents ML-75V Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check of Replacement Safety Precautions SectionStandards SPECIFICATIONS/COMPONENT Identification SpecificationsSpecifications Component Identification Page Installation Procedures Location RequirementsUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements General Exhaust Ductwork InformationOutside Ductwork Protection Page Page Page Electrical Information Electrical RequirementsGas and Steam Models Only Page Single-Phase Electrical Lead Connections Page GAS Information Type of GAS Page Page Operating Steam Pressure Steam InformationPage Compressed Air Supply Air Pressure Page Preparation for OPERATION/START-UP Preoperational Tests Basket Tumbler Coating Preoperational Instructions Coin Models NON-COIN Models Shutdown Instructions Dual Timer DryersReversing Timer SPIN/DWELL Adjustments Parts SERVICE/PARTS InformationService Warranty Information Returning Warranty CardsWarranty Returning Warranty PartsPage Routine Maintenance CleaningAdjustments LubricationProcedure for Functional Check Replacement Components Page Data Label Information Serial Number Dual Timer Manual Reset Burner HI-LIMIT InstructionsPhase S. In Action Fire Suppression System F.S.SInstallation Before YOU Start Check Local Codes and PermitsTypical water supply Optional Manual Bypass S. Theory of Operation S. Water Valve Check Starting a Cycle When Computer is in F.S.S. is Disabled Mode ADC Part No 05/26/05