IMPORTANT: For extended ductwork runs, the cross section area of the ductwork can only be increased to an extent. When the ductwork approaches the maximum limits noted in this manual, a professional heating, venting, and air conditioning (HVAC) firm should be consulted for proper venting information.

ALL ductwork should be smooth inside with no projections from sheet metal screws or other obstructions which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the ductwork.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (ALL the way around). The duct must be centered within this opening.

a.Outside Ductwork Protection

1)To protect the outside end of horizontal ductwork from the weather, a 90° elbow bent downward should be installed where the exhaust exits the building. If the ductwork travels vertically up through the roof, it should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and the nearest obstruction.

IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

16

Image 20
Contents ML-75DII Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Routine Maintenance Section Important InformationSafety Precautions What to do if YOU Smell GASStandards SPECIFICATIONS/COMPONENT Identification SpecificationsSpecifications Component Identification Page Installation Procedures Location RequirementsUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Exhaust Requirements Horizontal VentingPage Page Page Page Electrical Information Electrical RequirementsMLS-75 Steam MLE-75 Electric Page Single-Phase 1Ø Electrical Connections Leads Page Page Page GAS Information Type of GAS Page Steam Information Operating Steam Pressure Page Compressed AIR Supply AIR Pressure Page Preparation for OPERATION/START-UP Preoperational Tests Basket Coating Preoperational Instructions Shut Down Instructions Parts SERVICE/PARTS InformationService Warranty Information Returning Warranty CardsWarranty Returning Warranty PartsPage Routine Maintenance CleaningDays Adjustments LubricationProcedure for Functional Check Replacement Components Page Page Reversing Timer SPIN/DWELL Adjustments Timing LegendData Label Information Data LabelData Label Manual Reset HI-LIMIT Instructions P O RTA N TFor Phase 6 Models Electric or Steam Models only