B. ELECTRICAL and GAS REQUIREMENTS

It is your responsibility to have ALL electrical connections made by a properly licensed and competent electrician to assure that the electrical installation is adequate and conforms with local and state regulations or codes. In the absence of such codes, ALL electrical connections, materials, and workmanship must conform to the applicable requirements of the National Electrical Code ANSI/NFPA NO. 70-LATEST EDITION, or in Canada, the Canadian Electrical Codes Parts 1 & 2 CSA C22.1-1990 or LATEST EDITION.

IMPORTANT: Failure to comply with these codes or ordinances and/or the requirements stipulated in this manual can result in personal injury or component failure.

The dryer installation must meet the American National Standard, National Fuel Gas Code ANSI Z223.1- LATEST EDITION, or in Canada, the Canadian Electrical Codes Parts 1 & 2 CSA C22.1-1990 or LATEST EDITION (for Electrical Connections) as well as, local codes and ordinances, and must be done by a qualified technician.

NOTE: Undersized gas piping will result in ignition problems and slow drying and can create a safety hazard.

The dryer must be connected to the type of gas (natural or liquid propane [L.P.]) indicated on the dryer data label. If this information does not agree with the type of gas available, contact the reseller who sold the dryer or contact the factory.

The gas input ratings shown on the dryer data label are for elevations up to 2,000 feet (609.6 meters), unless elevation requirements of over 2,000 feet (609.6 meters) were specified at the time the dryer order was placed with the factory. The adjustment for dryers in the field for elevations over 2,000 feet (609.9 meters) are made by changing the burner orifices. If this adjustment is necessary, contact the reseller who sold the dryer or contact the factory.

NOTE: Any burner changes must be made by a qualified technician.

C. OPERATIONAL SERVICE CHECK PROCEDURE

After performing any service or maintenance function, an operational check should be performed to insure that ALL components are performing properly.

1.Make a complete operational check of ALL the operating controls to insure that the timing is correct, temperature selection switches are functioning properly.

2.Make a complete operational check of ALL safety related circuits, door switches, hi-limit thermostat, sail switch, cycling thermostats, etc.

1 6

Image 20
Contents AD-310 Phase Retain This Manual In a Safe Place For Future Reference Important Note to PurchaserFor Your Safety Page Table of Contents Section Procedure for Functional Check of Replacement AD-310 Reference Guide Base Section Section Explosion could ResultStandards Cleaning LiquidsAT 80 PSI 5.51 Bars Lubrication Every 3 MonthsAdjustments Days After Installation and Every 6 Months ThereafterSpecifications and Dimensions Dimensions Obligation Obligation Installation Requirements ENCLOSURE/AIR SUPPLY/EXHAUST RequirementsOperational Service Check Procedure Electrical and GAS RequirementsHeat Section Direct Spark Ignition DSI System COMPONENTS/FUNCTIONSVAC Direct Spark Ignition DSI Modules 225º F 107º C Thermostat Redundant Gas Valve First Visual Check Second Visual Check Third Visual Check Troubleshooting the Direct Spark Ignition DSI System ManometerPage Page Page First Visual Check Second Visual Check Third Visual Check With a Flame DSI Ignitor/Flame-Probe Assembly Adjustments Page Flash Green Continuously Page With a Flame DSI Ignitor/Flame-Probe Assembly Adjustments Page Light RED Continuously Page Createapotentialsafety Hazard Made of Brass and can be Easily DamagedSteam Coil System Operation General OverviewPage Page Page Page Sprinkler System Description MAN3488 Page Supplies Before Servicing the Dryer Page Page Tilting System Description Page Page Page Page Page AIR JET Assembly Page Blower Squirrel Cage Fan Motor Assembly Page Page Important do not Overtighten V-BELTS Important do not Overtighten V-BELTS Page Page FILTER/REGULATOR Assembly Regulator OperationDoor Systems Manual Doors Automatic Doors Page Page Page Control and Electrical System Ladder Diagram Page Button does not Disable the High Voltage to the Dryer Page ºC + ºC + ºK Page Page Page Page Page Page Tumbler/Drum SECTION. Serious Injury can Result Tumbler/Drum SECTION. Serious Injury can Result Basket Tumbler Drive System Important do not Overtighten Turnbuckle Important do not Overtighten Turnbuckle Page Page Important do not Overtighten Turnbuckle Page Page Page Phase 7 OPL System Diagnostics Inputs RED Outputs Green Fdrc RED L.E.D Lint RED L.E.D 100 101 Troubleshooting Drive motor is not operating does not start Impellor fan motor is not operating does not start 105 106 Dryer operates but is taking too long to dry Excessive noise and vibration 109 Procedure for Functional Check Replacement Components 111 ADC 450049 1- 09/14/00-25