5.4Gas pipe entry must come through the right hand side of the box. The rubber seal must be cut using a sharp knife to allow the isolating elbow to pass through it. Ensure the rubber is not damaged when doing this.

A means of isolation is provided with the appliance. This must be fitted to the supply pipe prior to installing the firebox.

6.INSTALLATION OF THE APPLIANCE

6.1Ensure that the fireplace opening is in compliance with the requirements of section 2 Site Requirements then proceed as follows:

A)CABLE RETENTION METHOD

6.2Mark the position of the 4 fixing holes on the rear of the fireplace opening and drill the holes using a No. 12 masonry drill bit. Insert the 4 fibre rawl plugs and screw the eyebolts in as far as possible leaving the eye horizontal. See diagram 4.

4

 

75 75

 

75 75

 

465

 

 

 

328

 

 

 

48

Hotbox

24

Convector

 

 

 

 

 

 

 

 

 

 

AR1204

 

 

AR1205

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.3Pass the 2 cables through the holes in the bracket on the back of the firebox and pull taut so that the stop ends sit

tightly against the top of the bracket. See diagram 5.

5

Hotbox

Convector

 

 

 

 

 

AR1156

 

AR1155

6.4Pass the cables vertically through the 2 sets of eyebolts and thread the ends through the holes in the lower back of the firebox. Pass the gas supply pipe through the hole in the rubber seal (refer to section 5.2) and push the appliance into place.

6.5Thread the cables through the tensioner bolts and push the threaded portions through the holes in the firebox so that the lock nut sits against the back wall (ensure that the nut is screwed fully up to the head of the tensioner to allow maximum adjustment).

6.6Slide the locking nipples onto the cables, pull the cables taut and tighten the locking screw. Adjust the lock nuts using a 10mm spanner until the silicone sealing strip forms a tight seal between the fireplace opening and the firebox flange. See diagram 6.

6

AR1157

6.7Coil up the surplus cable and locate in the back of the fire box.

NEVER SHORTEN THE CABLES, THEY WILL BE REQUIRED WHEN SERVICING THE APPLIANCE.

13

Image 13
Contents Logic Hotbox & Convector Fire Contents FLUE CHECK APPLIANCE COMMISSIONING CHECKLISTGAS CHECK Lighting the Fire User InstructionsTurning the Fire OFF Lighting the Fire with a MatchArrangement of Fuel BED Components Cleaning the FireCoal Layout Front ROW Coal Layout Using Flat Fire Fronts Oxygen Depletion Sensor Installation DetailsFlame Failure Device 10. ‘RUNNING IN’Technical Specification Installation InstructionsMinimum Debris Collection Flue and Chimney Requirements Site RequirementsAppliance Location GAS Supply Installation Cable Retention Method Installation of the ApplianceScrew Fixing Method AR1163 AR1160 AR1174 AR1171 Commissioning Installation / CommissioningServicing Servicing InstructionsServicing Requirements Servicing Instructions Fault Finding Charts Fault Finding Charts General Replacing PartsIgnition Lead Gas valve Mag unit 9th Service 10th Service Service Records