Hampton Direct U32-LP2 GAS Insert Aeration System, Optional Brick Panel, Natural Gas Propane

Page 8

INSTALLATION

9)Connect the 2nd liner to the exhaust collar marked with an "E", seal connection with high temperature silicone. Secure with gear clamp.

NOTE: 1) Final gas connection should be made after unit is in place to avoid damage to line when pushing the unit into position.

2)Mill-pac may be used instead of high temperature silicone and screws may be used instead of gear clamps at connections of liner to inlet and vent collars.

2)Loosen the "IN" and/or "OUT" pressure tap(s), turning counterclockwise with a 1/ 8" wide flat screwdriver.

3)Attach manometer to "IN" and/or "OUT" pressure tap(s) using a 5/16" ID hose.

4)Light the pilot and turn the valve to "ON" position.

5)The pressure check should be carried out with the unit burning and the setting should be within the limits specified on the safety label.

6)When finished reading manometer, turn off the gas valve, disconnect the hose and tighten the screw (clockwise) with a 1/8" flat screwdriver. Note: Screw should be snug, but do not over tighten.

GAS INSERT

AERATION SYSTEM

The air shutter can be adjusted by moving the adjusting wire up or down. The wire is ac- cessed through the bottom louver opening. Open the air shutter for a blue flame or close for a yellower flame. The burner aeration is factory set but may need adjusting due to either the local gas supply or altitude.

Minimum Air Shutter Opening:

3/16" Natural Gas

1/4" Propane

OPTIONAL

BRICK PANEL

1)Unwrap the brick pattern panels from the protective wrapping.

2)Remove the glass front if it is already installed, see page 11.

3)Put the rear brick panel flat against the back of the unit.

4)Before installing the side brick panels, loosen the screws for the brick tabs enough so that you can slide the brick tabs on to the screws easily but that the tabs are secure. For the location of the side brick tab screws see diagram 1.

GAS PIPE

PRESSURE TESTING

The appliance must be isolated from the gas supply piping system by closing its individual manual shut-off valve during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 psig. (3.45 kPa). Disconnect piping from valve at pres- sures over 1/2 psig.

The manifold pressure is controlled by a regu- lator built into the gas control, and should be checked at the pressure test point.

Note: To properly check gas pressure, both inlet and manifold pressures should be checked using the valve pressure ports on the valve.

1)Make sure the valve is in the "OFF" position.

Aeration Adjustment Wire

PULL= Open

PUSH = Close

CAUTION: Carbon will be produced if air shutter is closed too much.

Note: any damage due to carboning re- sulting from improperly setting the aer- ation controls is NOT covered under warranty.

Note: Aeration Adjustment should only be performed by an authorized FPI Installer at the time of installation or service.

Diagram 1

5)Remove the brick tabs and slide the side brick panels into position. See diagram 1. Install the brick tabs. See diagram 2.

Diagram 2

8

U32-2 FPI Direct Vent Gas Insert

Image 8
Contents U32 Gas Insert FPI GAS Insert To the NEW OwnerTable of Contents Safety Label Installation Manufactured Mobile Home Additional Requirements Minimum Fireplace Dimensions Clearances to CombustiblesMaterials Required Venting Flue Liner InstallationGAS Connection GAS Pipe Pressure Testing GAS Insert Aeration SystemOptional Brick Panel Natural Gas PropaneLOG SET Installation Rear View Faceplate Assembly Diagram Faceplate & Trim InstallationRear View Trim Assembly Diagram Optional Double Door Fire Screen Standard Flush DoorOptional BAY Door Optional BAY TrimRemoving Bay Door Robert Shaw Extension knobs for Bay Front onlyHampton Cast Faceplate Installation Hampton Cast Faceplate Grill Installation Side Hook Diagram SlotsHampton Logo Left Hand Side Faceplate Diagram U32 Grill Stop BracketThermostat Wire Table Optional RemoteControl Final CheckWiring Diagram Electrical Grounding InstructionsOperating Instructions Maintenance Instructions Copy of Lighting Instruction PlateMaintenance FAN Maintenance Bay Glass RemovalTo remove fan Grate screwsValve Replacement Install a new gasket and reinstall the valve assemblyShut off the gas supply Heat Gasket ShieldParts List Main AssemblyBurner Assembly & LOG SET Bay Door Flush DoorFaceplate Assembly Hampton Cast Faceplate Assembly Warranty Warranty LifetimeInstaller Please complete the following information