5.Cut all of the cable ties coming from the tube holder following the two wires from the tube holder to where it terminates. Note: there will be two different termination points for each tube holder. Once this has been located, cut the wires (marking them to ensure easy replacement).

6.The tube holder(s) can now be removed by pushing the holder into the main chamber and feeding the wires through the cut-out.

7.Replace tube holder(s). (Part number 36-0003-01)

8.In order to refit the tube holder, reverse the above procedure using butt crimps to reconnect the wires.

Note: If more than one tube holder is to be replaced, the wiring schematic diagram may be of assistance.

Replacement of starters

1.Locate the starter to be changed. These are positioned in a vertical row on the right hand side of the internal chassis assembly.

2.Turn starter(s) 30 degrees anti-clockwise and then pull out of the holder.

3.Reverse above procedure with recommended starter.

Replacement of starter holder

1.Locate the starter holder to be changed. It is located on the right hand side of the internal chassis assembly.

2.Lever off the starter holder using a flat bladed screwdriver. The holder should now be loose.

3.Replace unit (part number 36-0005-01). This is achieved by first loosening the internal reflector which is held in place with eight screws. The screws can be located in the chamber of the crosslinker - two on the left, two on the right and four on the top of the chamber.

4.To replace the starter holder first push the center of the two black spigots, which hold the starter holder (x2) away from you i.e. towards the crosslinker chamber. As the reflector has been loosened, this should be done fairly easily with a small, flat-bladed screwdriver.

5.The starter can now be relocated.

-14 -

Image 16
Contents Ultraviolet Crosslinkers Contents Description and Specifications Important Safety InformationIntroduction Features ElectricalCL-1000 Shortwave Crosslinker CL-1000L Longwave CrosslinkerOperation UV Crosslinkers UVP UV Crosslinkers UVP Applications MAINTENANCE, Care and Cleaning of the Crosslinker UV Wavelength Calibration Procedure Changing the UV WavelengthUV Crosslinkers UVP Crosslinker Calibration Procedure Equipment necessary Voltage Range for U4 Range for U5 Replacement Parts and Servicing Procedures Operations with TOP Cover RemovedReplacement of tube holders General Servicing ProceduresOperations With Top Cover Removed Removal of top cover Replacement of starters Replacement of starter holderReplacement of main connector Replacement of fuse holdersReplacement of main switch Replacement of PCB Replacement of UV sensorReplacement of membrane panel Replacement of reflector General Items Changing fuses Changing plastic feetSchematic Wiring Diagram Corporate Headquarters UVP, Inc