UVPS 81-0112-01 Rev C manual Replacement of fuse holders, Replacement of main connector

Page 17

UV CROSSLINKERS

UVP

6.To secure the starter holder, place the holder in your right hand and with your left hand in the chamber, press the now loosened reflector adjacent to the holder inwards. This will push the black spigots inwards thereby securing the starter holder.

7.Re-fit the reflector.

Replacement of fuse holders

These are located at the back of the unit just above the mains connector. There are two fuses in separate holders. Replacement is the same for both.

1.Cut back the heat shrink on the two wires.

2.Unsolder both connections and pull from the holder.

3.Unscrew the nylon nut and push the holder out through the back of the unit.

4.To replace-reverse the above procedure.

Replacement of main connector

This is located at the back of the unit below the fuse holders.

1.Cut back the heat shrink on the three wires.

2.Unsolder the three connections and pull from connector.

3.Release main connector by holding the nuts with a spanner and then on the outside back of the unit, release the two screws one at a time (using a screwdriver). The main connector should now be loose.

4.To replace-reverse the above procedure.

Replacement of main switch

This is located on the front panel below the membrane pad.

1.Remove the wires noting their position.

2.Remove the switch by pushing it out from the back towards the rear of the front panel.

3.Push in the new switch and re-connect.

-15 -

Image 17
Contents Ultraviolet Crosslinkers Contents Introduction Important Safety InformationDescription and Specifications Electrical FeaturesCL-1000 Shortwave Crosslinker CL-1000L Longwave CrosslinkerOperation UV Crosslinkers UVP UV Crosslinkers UVP Applications MAINTENANCE, Care and Cleaning of the Crosslinker Changing the UV Wavelength UV Wavelength Calibration ProcedureUV Crosslinkers UVP Crosslinker Calibration Procedure Equipment necessary Voltage Range for U4 Range for U5 Operations with TOP Cover Removed Replacement Parts and Servicing ProceduresOperations With Top Cover Removed Removal of top cover General Servicing ProceduresReplacement of tube holders Replacement of starter holder Replacement of startersReplacement of main switch Replacement of fuse holdersReplacement of main connector Replacement of membrane panel Replacement of UV sensorReplacement of PCB Replacement of reflector Changing plastic feet General Items Changing fusesSchematic Wiring Diagram Corporate Headquarters UVP, Inc