Haier AD362AMERA, AD482AMEAA, AD362AMEAA, AD282AMERA, AD182AMEAA Drainage Test, Procedures

Page 17

Installation Manual For Indoor Unit

(d)When constructing drain piping for several units, position the common pipe about 100 mm below the drain outlet of each unit as shown in the sketch. Use VP-30(11/4") or thicker pipe for this purpose.

(e)Be sure to provide heat insulation to hard PVC pipes of indoor placement.

(f)Do not ever provide an air vent.

(g)The height of the drain head can be elevated up to a point 500 mm above the ceiling, and when an obstacle exists in the ceiling space, elevate the piping to avoid the obstacle using an elbow or corresponding gadget. When doing this, if the stretch for the needed height is higher than 500 mm, the back- flow quantity of drain at the event of interruption of the operation gets too much and it may cause overflow at the drain pan. Therefore, make the height of the drain pipe within the distance given in the sketch below.

(h)Avoid positioning the drain piping outlet at a place where generation of odor may be stimulated. Do not lead the drain piping direct into a sewer from where sulfur gas may generate.

Drainage Test

Secure the elevation as high as possible (approx. 100 mm)

 

A downhill grade of

VP 30

 

1/100 or more

 

 

290~325mm

dimension)

 

Drain hose

 

Right overhead

600 local drain up

 

 

 

 

Joint for VP 25

(Maximum

 

 

 

 

(Local procurement)

1Conduct a drainage test after completion of the electrical work.

2During the trial, make sure that drain flows properly through the piping and that no water leaks from connections.

3In case of a new building, conduct the test before it is furnished with the ceiling.

4Be sure to conduct this test even when the unit is installed in the heating season.

Procedures

1Supply about 1000 cc of water to the unit through the air outlet using a feed water pump.

2Check the drain while cooling operation.

Remove grommet. Make sure to install it back after test.

Insert water supply hose for 20 mm ~ 30 mm to supply water.

(Insert hose facing toward bottom.)

Attached drain hose clamp

Main unit

Drain piping

 

Drain situation can be checked with transparent socket

Pour water into a convex joint.

(In the electrical work has not been completed, connect a convex joint in the drain pipe connection to provide a water inlet. Then, check if water leaks from the piping system and that drain flows through the drain pipe normally.)

16

Image 17
Contents Please keep this manual carefully and safely Duct Type AIR ConditionerTable of Contents Disposal of the old air conditioner Circuit breaker may be necessary Positive draining Safety PrecautionsNeither stand on the air conditioner nor Outdoor Machine is adaptive in following situationDuct Air outlet Air inlet Parts and FunctionsUnit fails to start MalfunctionCooling or heating is not sufficient Cooling is not sufficientFollowings are not malfunction Case of Auto mode, operation mode is changed automatiWater flowing sound is heard This is caused by heat expansion or contraction of plasticsPoints to observe Care and MaintenanceFor Preparation of HeatingHot Keep Installation place Is The Unit Installed CorrectlyWhen you change your address or the installation place For inspection and maintenanceSerious injury are listed Installation Manual For Indoor UnitCombination 416mmPreparation of indoor unit Hanger bolts installation Avoid installation and use at those places listed belowAdjusting to the levelness Installation of indoor unitTap selection on blower unit Drain PipingDrainage Test ProceduresConnection of suction, exhaust ducts Installation work for air outlet ductsBlowout duct Model Wiring connectionRemarks Trouble ShootingShows resumable fault, shows it is not resumable fault Degree Resumable ifHaier Group