Haier AB182XCERA, AB142XCERA Installation of water drainage pipe, Less than 75mm Less than 500mm

Page 16

Installation Procedures

4. Installation of water drainage pipe

(1) Install water drainage pipe

Pipe diameter shall be equal or larger than that of connecting pipe (Pipe of polythene; size: 25mm; O.D.: 32mm )

Drainpipe should be short, with a downward slope at least 1/100 to prevent air bag from forming.

If downward slope of drainpipe cannot be made,lifting pipe shall be installed. Keep a distance of 1-1.5m between suspending bolts, to make water hose straight.

1-1.5m

slope over 1/100

Use the drainage hose and clip provided with unit.

Insert water pipe into water plug until it reaches the white tape.

Tighten the clip until head of the screw is less than 4mm from hose.

Wind the ddrainage hose to the clip using seal pad for heat insulation.

Insulate drainage hose in the room.

 

Large size seal pad

Clip

(accessory)

 

Clip

 

 

 

 

 

 

 

 

 

Tape(white)

 

 

 

 

 

 

 

 

 

 

 

 

Draingage hose

Less than 4mm

5. Cautions for the water drainage lifting pipe

Installation height of water drainage lifting pipe shall be less than 280mm

There should be a right angle with unit ,300mm from unit.

Less than 300mm

1-1.5m Suspending bracket

Drainage hose

Drainage hose

 

 

Less than 280mm

 

220mm

220

500mmthan

 

Clip

 

Water drainage

 

 

 

lifting pipe

 

 

 

< Note >

 

 

Less

 

 

 

 

 

Less than 75mm

Less than 500mm

The slope of water drainage hose shall be within 75mm , make the drainage plug not to bear excessive force.

If several water hoses join together, of as per following procedures.

100mm ¸over

Slope less than 1/100

Connection drainage hose with a T-joint

 

Specifications of the selected drainage hoses shall meet the requirements for the unit running

14

Image 16
Contents No.0010577258 Contents Disposal of the old air conditioner Applicable ambient temperature range Refrigerating circuit is leak-proofRemote Control Main Points of OperationOperation of Air Conditioner Minute Protection FunctionDefrosting Function Prevent Cool Air Blowing OffHints Parts and Functions Swing louverOperating Control Panel Air Inlet GrilleSafety Cautions Dont operate the air conditioner with damp hands Maintenance Clean the unitClean the air filter Clean indoor outdoor unitSeasonal Reserve Post-season Care Pre-season CareWhen Trouble Happens Cooled air blown out when heatingInsufficient cooling or heating Insufficient coolingCustomer Need-to-know Using DirectionsCustomer Need-to-know Selection of Installation Place Installation ProceduresInstallation Preparation After installation on the ceiling Installation of indoor unitCase of ceiling already exists Installation of water drainage pipe Less than 75mm Less than 500mmInstallation of Ornament Panel Install ornament panel on indoor unitPiping Connection AB092XCERA AB122XCERAElectrical Wiring Wiring methods Wiring method of ring terminalInstructions to installation Indoor unit communication addresses settingIndoor Trouble Shooting Followings are not malfuncitionOFF Abnormal communication Haier Group