2.0INSTALLATION

Read this entire installation section before starting installation. This section details dimensional, electrical and piping information and specifications that affect the placement of the PFH unit in rela- tion the connected evaporator unit, other outside units, barriers and walls.

Be particularly mindful of service and airflow clearances and maximum equirvalent piping distances and in elevation differences between PFH and connected evaporator unit. Consult and confirm appli- cations with your Emerson Network Power representative when applications exceed any of these specifications.

2.1Equipment Inspection

When the unit arrives, inspect all items for any visible or concealed damage. Report any damage to the carrier immediately and file a damage claim; send a copy of the claim to Emerson Network Power or your local Emerson sales representative.

If possible, maintain equipment and packaging until it is at the installation location.

2.2Location Considerations

To ensure an adequate air supply, locate all condensing units in a clean-air area, away from loose dirt and debris that can clog the coil. Avoid ground-level sites with public access or areas that are exposed to heavy snow accumulation. Locate unit to allow maximum security and maintenance accessibility.

Do not locate condensing units near steam, hot air or fume exhausts. Do locate units at least 18 in. (457mm) from walls, obstructions or adjacent units. For multiple unit installations, space unit so that the hot condenser exhaust air is not directed toward the condenser air inlet of an adjacent unit.

Install a solid base at least 2 in. (51mm) higher than the surrounding grade and 2 in. (51mm) larger than condensing unit base dimensions and capable of supporting the condenser’s weight.

2

Image 6
Contents Liebert Prop Fan Condensing Unit Example PFH037A-PL7 = 380/415-3ph-50HzTable of Contents Figures Prop Fan Condensing Units Optional EquipmentEquipment Inspection Location ConsiderationsModel Numbers Dimensional Data, in. mm Lb. kg 60Hz 50Hz Dimensional DataNet Weight Cabinet and floor planning data, horizontal air dischargeFootprint Dimensions Wall Mounting Piping and Electrical Connections Electrical and piping connections, horizontal air discharge152 PFH096A- LGeneral piping arrangement Electrical field connections, 1- to 5-ton units Top Air Discharge ModelsElectrical field connections, 8-ton units Single-phase, 1-3 ton model schematic, typical Three-phase, 3-5 ton model schematic, typical Three-phase, 8 ton model schematic, typical Piping Considerations Piping for Elevation Differences between PFH and EvaporatorEvaporator Condensing UnitEquivalent lengths for various pipe fittings, ft m Refrigerant charge in Liebert pre-charged R-407C line sets Pre-Charged Line SetsField-Fabricated Line Sets Line Size Length Charge R-407C Ft. m Lb-oz kgLiebert PFH unit charge levels and coupling size Recommended line sizes, OD CuLine charges refrigerant per 100 ft m of Type L copper tube Installation of Piping to UnitsPiping connection sizes and torque Line Size OD Cu Coupling Size Torque, lb-ft. N-mFilter Drier Selection and Installation Install the New Condensing UnitRemove Existing Condensing Unit General System Charge Requirements Evaporator Charge LevelsEvaporator Charge R-407C Indoor Unit Models Oz kg Low-Voltage Control Wire Connections Low-Voltage Control Wire SizingElectrical Connections Electrical Data Nominal Input Voltage- Phase Capacity ElectricalNominal Input Voltage-Phase Capacity Electrical Electrical data-High ambient models 105F/41C 60HzElectrical data-Quiet-Line models 95F/35C 60Hz Electrical data-High ambient models 105F/41C 50HzChecklist for Completed Installation Electrical data Quiet-Line models 95F/35C 50HzCompressor High Head PressureLiebert Lee-Temp Flood Back Head Pressure Control Adjustment Hot Gas BypassOperation Hot gas bypass diagram Electrical Failure-Burnout GeneralCompressor Failure Mechanical FailureCompressor Replacement Field Charge Verification Field verification chargeModel Numbers 407C 60 Hz 50 Hz Oz kg Troubleshooting Problem Cause RemedyUni Single-Phase&Three-Phase UPS Environmental SystemsWeb Site Monitoring Etwo