Changing Speeds
The belts in the head of the mill/drill must be rearranged to change speeds. A chart on the belt cover shows the belt positions needed to make the mill/drill run at the desired speed.
To change speeds:
1.UNPLUG THE MILL/DRILL!
2.Loosen the motor lock screw (shown in Figure 19), so the motor is free to pivot.
5.Locate the desired speed on the belt cover speed chart or on Page 22 and move the V- belts to the desired
For Example: As indicated in the speed chart (Figure 21), a belt combination of
Note: Both belts may have to be removed before certain speed changes can be made. It is normal for the idler bracket to move in response to a belt change.
Figure 19. Motor lock screw.
3.Pivot the motor to loosen the belt tension.
4.Loosen, but do not remove, the two idler bracket hex bolts shown in Figure 20.
Figure 20. Idler bracket hex bolts.